Meeting 6-5-2015

Date: 6th may 2015
Time: 15:00 UK time
Attendance: Paul K, Chris Heit, Ray G, Adam D, Edward O,
Apologies: Melissa

Agenda and Minutes

Actions from Last Meeting

  • Kalman doesnt work on straights. - Chris Hunt looking to fix. Stands.
  • Real data unpacking broken. A proper summary of the issue, its status and timeline to be presented next week. - Paul.
    Still Broken, Paul expects to understand why this is broken next week.
  • Software update from Paul next meeting - PK.
  • Prepare a tag out lock out procedure to stop people turning things off that we don't want them to (He etc. - Add the above to the controls and monitoring alarms so that if the above happens we know - Pierrick. No Update
  • Add to John Govans' rota for daily walk round to test our setup. - Pierrick. No Update
  • Look at docs to determine what to release as MICE notes and how - MU - ONGOING
  • Update in depth Tracker schedule and agree with Ed and Craig. - E.O. Speak to Melissa/Craig next week.
  • Cryo lids still needed. Melissa to ask Geoff or Kevin. Stands.
  • Put the above on the data section of the Tracker wiki. -MU. Stands
  • EO to speak to C. Heidt when performing calibrations.

1. Status of hardware, commissioning work and ongoing plan EO, AB, CMW, PR, MU

At end of last visit:
  • 4 cryos reading out
  • cryo 2 was struggling with temperature regulation (~9.05K), no thermal overhead. Plan to switch cryocoolers to 60Hz to gain 0.5W cooling capacity.
  • damaged LVDS lead from cryo 3 observed. spare to be run on next visit.
EO Will visit next week:
  • Will perform bias calibration scans(longer scan, more data).
  • Will check bias results.
  • Will Integrate remaining code with the tracker IOC.

2. Software: PK, AD, CH

In particular this week:
  • Data unpacking - next week see actions
  • Kalman - next week see actions
  • DAQ in data structure - see above
  • CDB mapping and bias calibrations

Geometry, Calibrations, Configurations, CDB - C. Heidt * Good, * Figured out 95% of mapping and has script to generate data. * Working with the CDB software. * Geometry, no update.

Monte Carlo

  • No Update, nothing left to be said.
  • Good not great.

Pattern Recognition - AD,

  • No update.
  • AD to talk to PK.
  • No method to get multiple tracks per trigger.

Online Displays - MU

  • 3/4 of the plots are now in and working and were used for mock data challenge. The other are the non-immediately-essentials and are coming soon.

Performance and Analysis -PK

  • Discussed in actions/software

Issues

Tracker Software Paper - AD, PK DR

Documentation - PK, AD, C. Heidt

4. Optimising the DAQ and Controls and Monitoring - EO, AB, PR
  • Limited resources to speed up DAQ at present, fully committed to commissioning efforts.
  • C&M additions will be added next week to tracker IOC.

5. MICE hall, inc Services hardware and requirements : CM okay

6. Step IV Analysis Readiness - MU

  • Unpacking and speed are biggest problems (PK)

7. Risks

7.1 Hardware

  • Daresbury electronics: vacuum, tracker interlocks
  • Reforming external waveguides (could lead to breakage)
  • Northside PRY (not us, but knock effect to us)

7.2 Software

  • Not yet able to test against multiple tracks per trigger with MC -Action for Durga
  • Real data unpacking broken DA

8. Tracker Documentation

We need to produce documentation for the control room and ISIS, for Steve B. We cannot necessarily get that far with operations and startup as we are not yet working with the CandM as we will but we can write something and finalise safety details.

8.1 Startup Procedure

8.2 Operations Procedure

8.3 Tracker Online Emergency Procedure

  • We have been asked to provide documentation for ISIS and eventually shifters in what to do in an emergency situation for the Tracker when running
    Documentation to Include:
    - schematics of the system
    - a list of associated checklists at power on, and who works through them.
    - a list of instructions to shifters on how to operate and monitor the system
    - emergency shutdown instructions
    - power-up instructions
    - trouble-shooting : what to watch for
    - a list of regular maintenance and safety checks

5. Other Items

  • Installation Manual - GB MU - ongoing
  • LED system - EO - External used for calib, Internal not used since Dec but will be used after gain and pedestals determined.
  • Hall probes - MU - Ongoing

AoB

  • Ray requests an urgent review of goals and milestones with a schedule.
  • Consider switching to a weekly meeting.

New Actions

Phone Details

  • The four digit company id: 4673 (callers from outside the UK)
  • The pin number: 419357

Phone numbers:

UK (Imperial College --preferred) 0845 545 4460 English
Austria 0820 4000 1503 English
0820 4000 15 02 German
Belgium 070 35 99 45 English
070 35 99 94 Dutch
070 35 98 66 French
Canada 1 712 432 2832 English
1 712 432 2844 French
Germany 01803 001 178 English
01570 248 8303 English (mobile)
01803 001 177 German
01570 248 8101 German (mobile)
Ireland 0818 270 007 English
Italy 848 390 166 English
848 391 819 Italian
Netherlands 0870 001 901 English
0870 001 909 Dutch
Poland 0801 003 543 English
0801 003 533 Polish
South Africa 087 550 0375 English
Spain 902 885 318 English
902 881 200 Spanish
Sweden 0939 2066 400 English
0939 2066 300 Swedish
Switzerland 0848 560 190 English
0848 560 378 French
0848 560 347 German
0848 560 385 Italian
United Kingdom (PowWowNow) 0844 4 73 73 73 English
United States 1 415 363 0833 English

Updated by George, Melissa over 8 years ago ยท 5 revisions