Project

General

Profile

Drawings » History » Version 70

Bayliss, Vicky, 20 April 2017 14:48

1 4 Bayliss, Vicky
h1. Technical Data and Drawings
2 2 Bayliss, Vicky
3 64 Bayliss, Vicky
h2. System Design
4 65 Bayliss, Vicky
5 43 Bayliss, Vicky
** System design:
6
*** attachment:H2SaftyFun.pdf
7
** Control system: 
8
*** attachment:H2CtrlSpec_V2.pdf
9 69 Bayliss, Vicky
*** attachment:H2CtrlSpec_V4_2.doc
10 45 Bayliss, Vicky
** Electrical system: 
11
*** attachment:H2Ctrl_Ex_Equip.doc
12 42 Bayliss, Vicky
13 64 Bayliss, Vicky
h2. DSEAR
14 65 Bayliss, Vicky
15 54 Bayliss, Vicky
** Zone drawing:
16
*** attachment:MICEH2-DSEAR_zone_dwg.pdf
17
*** attachment:MICEH2-DW-150610_Zoning_drawing_Step_IV.pdf
18
** Overall DSEAR RA
19
*** attachment:Overall_DSEAR_RA_MICEH2-RA-110906.doc
20
*** attachment:MICEH2-RA-150609_DSEAR_RA.pdf
21 39 Bayliss, Vicky
22 64 Bayliss, Vicky
h2. P&ID
23 65 Bayliss, Vicky
24 41 Bayliss, Vicky
attachment:Hydrogen_System_Baseline_Layout_18June12.pdf
25 47 Bayliss, Vicky
attachment:Hydrogen_System_Baseline_Layout_15-03-20.pdf
26 52 Bayliss, Vicky
attachment:Hydrogen_System_Baseline_Layout_15-06-05.pdf
27 68 Bayliss, Vicky
attachment:Hydrogen_System_Baseline_Layout_19-04-17.pdf
28 20 Bayliss, Vicky
29 64 Bayliss, Vicky
h2. Hydrogen Venting
30 65 Bayliss, Vicky
31 49 Bayliss, Vicky
** Harrison report - attachment:MICE_Hydrogen_Venting_Report_01.pdf
32 55 Bayliss, Vicky
** Harrison report - attachment:MICE_Hydrogen_Venting_Report__02.pdf
33 51 Bayliss, Vicky
** Relief line proposal - attachment:Relief_line_proposal.pdf
34 20 Bayliss, Vicky
35 64 Bayliss, Vicky
h2. KEK drawings and notes
36 65 Bayliss, Vicky
37 32 Bayliss, Vicky
** Absorber III Report - attachment:Absorber-III-Report.pdf
38 26 Bayliss, Vicky
** Absorber drawings:
39 30 Bayliss, Vicky
*** attachment:KEK_Absorber-1.dwg
40 31 Bayliss, Vicky
*** attachment:KEK_Absorber-2.dwg
41
*** attachment:KEK_Absorber-3.dwg
42 1 Bayliss, Vicky
** Complete translated material certificates - attachment:Complete_material_certs_Translated.docx
43 26 Bayliss, Vicky
** Photos of KEK absorber testing:
44 29 Bayliss, Vicky
*** attachment:Absorber_Testing_at_KEK_1.jpg
45 25 Bayliss, Vicky
*** attachment:Absorber_Testing_at_KEK_2.jpg
46
*** attachment:Absorber_Testing_at_KEK_3.jpg
47
*** attachment:Absorber_Testing_at_KEK_4.jpg
48
*** attachment:Absorber_Testing_at_KEK_5.jpg
49
*** attachment:Absorber_Testing_at_KEK_6.jpg
50
*** attachment:Absorber_Testing_at_KEK_7.jpg
51
*** attachment:Absorber_Testing_at_KEK_8.jpg
52
*** attachment:Absorber_Testing_at_KEK_9.jpg
53
*** attachment:Absorber_Testing_at_KEK_10.jpg
54
*** attachment:Absorber_Testing_at_KEK_11.jpg
55
*** attachment:Absorber_Testing_at_KEK_12.jpg
56 20 Bayliss, Vicky
57 64 Bayliss, Vicky
h2. Window drawings and FEA analysis
58 65 Bayliss, Vicky
59 35 Bayliss, Vicky
** Window drawing - attachment:Absorber_Window.dwg
60 34 Bayliss, Vicky
** Thickness measurement of window at LBNL Report - attachment:MICE_Al_Window_1.pdf
61 46 Bayliss, Vicky
** Interim report on window assessment - attachment:Interim_report_on_window_assessment_based_on_CMM_profiles.pdf
62 1 Bayliss, Vicky
** Video of burst test - attachment:Window_burst.mp4
63 58 Bayliss, Vicky
** Pressure Test Certificate - attachment:70025_Pressure_Test_Certificate_TD_10085_1044_A.pdf
64 57 Bayliss, Vicky
** MICE-Absorber system safety review meeting - attachment:MICE-Absorber_system_Safety_Review.pdf
65 56 Bayliss, Vicky
** Report on Safety window failure - attachment:MICEH2-TR-150522_Safety_window_failure_note.pdf
66 34 Bayliss, Vicky
67 66 Bayliss, Vicky
h2. Electrical drawings
68
69 67 Bayliss, Vicky
** Conn 10 - attachment:204_77513_1_WHT.pdf
70
** Conn 9 - attachment:204_77513_2_WHT.pdf
71
** Conn 8 - attachment:204_77513_3_WHT.pdf
72
** Conn 11 - attachment:204_77513_4_WHT.pdf
73
** KEK absorber wiring - attachment:204_77513_5_WHT.pdf
74 66 Bayliss, Vicky
75 64 Bayliss, Vicky
h2. Absorber Surface Defect
76 65 Bayliss, Vicky
77 61 Bayliss, Vicky
** Report - attachment:20160615_Inspection_of_the__LH2_absorber_surface_imperfection.pdf
78 60 Bayliss, Vicky
** X-ray and Dye Penetrant test (Aaplus Aerospace) - attachment:STFC_Certs.pdf
79 33 Bayliss, Vicky
** Metrology: 
80
*** attachment:Beam_Window_Main_Report.pdf
81
*** attachment:Housing_Main_Report.pdf
82
*** attachment:DSCN0694.JPG
83 9 Bayliss, Vicky
84
85 64 Bayliss, Vicky
h2. Absorber Assembly 
86 65 Bayliss, Vicky
87 37 Bayliss, Vicky
** Assembly instructions - attachment:Hydrogen_absorber_assembly.docx
88
** Assembly review - attachment:MICE-Absorber_system_Safety_Review.pdf
89 62 Bayliss, Vicky
** Re-assembly and installation of the absorber Summer 2016
90 63 Bayliss, Vicky
*** attachment:20160727_Absorber_indium_seal.pdf
91
*** attachment:Absorber_MLI_Wrapping.pdf
92 38 Bayliss, Vicky
93 9 Bayliss, Vicky
h1. File List