  • CMcW: to trace trigger signal to FC datalogger.
  • PW: to modify purge sequence limits in agreement with JB.
  • AK/PW: to test permissions of required connections HMI to PLC.
  • MT/JB: Ensure D. Haines witnesses test of quench valve and complete appropriate documentation.
  • JB: Atex rating of everything in H2 shed.
  • JB: to prepare rota on 'limited call-out' basis
  • CW: to contact HR re 'on-call' times.
Actions defined Preliminary H2 tour

Monitoring and archival of data - PF/AK
Neon Run
Current technical
Documentation
Timetable
Next meeting
AoB