Actions
2017-08-03-LH2¶
Notes¶
Present: AK, PH, PF, MT, JT, HN, KL
- Actions
- Action on CMcW to trace trigger signal to FC datalogger.
- Stands.
- Action MT/JB to agree and implement testing of quench valves.
- Done. System works. Not yet clear if it has been witnesed. Action changed to ensure that test is witnessed and documented.
- Action PW to modify purge sequence limits in agreement with JB.
- Stands.
- Action AK/PW to test permissions of required connections HMI to PLC.
- Stands.
- Action CMcW/JB to search archiver for FC radiation shield temp & helium pressure excursions.
- Done. PH gave plot to JB. Features of quenches identified.
- Action PF/AK to propose IOC test program for next week.
- Done. IOC isolation has been implememted successfully. Firewall is open while we are in development mode.
- Action AK/JB to arrange further meeting on alarm handler development
- Done. Meeting held on 01Aug17. Parameters were specified. Spreadsheet has been updated. Outtanding issue is that parameters can not be set with firewall up. So need to hard-code limits in IOC.
- Action JB/PF to agree wiki page for paperwork.
- Done. This is teh document pge under operations.
- Action JB Atex rating of everything in H2 shed.
- Stands.
- Action KL discuss with JT final paperwork required - note ISIS requires document giving clear instruction for ISIS MCR
- Done. Documentation defined in the OPI provided by AN.
- Action JB to prepare rota on 'limited call-out' basis
- Stands.
- Action CW to contact HR re 'on-call' times
- Ongoing.
- Action on CMcW to trace trigger signal to FC datalogger.
- Actions defined Preliminary H2 tour
- Actions noted on the tour by AN:
- Arrange final documentation review
- Stands.
- Completion of Hazop requirements
- Stands.
- Correct the labelling on absorber on GUI diagram
- Done.
- Apply labels to pipes in loading bay area
- Check.
- Secure crash barriers around charging enclosure to roadway
- Stands.
- Check valve panel area is correctly identified on ATEX zoning drawing and apply ATEX zone notice to area
- Stands.
- Check that an alarm is provided in event of extract fans/pumps failing
- Stands.
- Check bonding of lightning conductor
- Stands.
- Arrange for testing and certification of the lift-off vent
- Stands.
- Arrange final documentation review
- The following actions all apply to the R5.2 LH2 roof enclosure:
- PH is in contct with A. Gallagher and relevant contractors. Trying to push to get commitment for work to be carried out. Will cost money.
- Arrange correct type of ATEX-compliant glands for vacuum pump motor wiring
- Add ATEX-compliant blanks to unused ports in vacuum pump motor terminal boxes
- Electrical connection to thermostat to be via ATEX-compliant gland
- Fit and test earth bond connection to heaters
- Check cable glands to gas detection heads and if necessary replace with ATEX-compliant ones
- Verify that the gas detection heads have been calibrated for hydrogen (rather than methane) and amend calibration plates
- Conduits for external lighting and beacons to be sealed to ATEX compliant standard
- Electrical bonding of all metalwork and equipment should be installed and tested
- Arrange a qualified inspection of the installation in line with the requirements of BS-EN60079-17, before the final safety tour
- AN note on initial safety tour:
- Actions noted on the tour by AN:
- Monitoring and archival of data - PF/AK
- IOC
- IOC now in use. Steady progress updating IOC in response to request. The only outstanding is the coding of the alarm limits.
- Alarm handler
- Values hvae been udated in spreadsheet, now need to migrate to alarm handler. Hard-code limits in IOC. Archiver is running.
- Request to have heater activity to be displayed on the GUI.
- IOC
- Neon Run
- Progress report JB/PW/MT/HN
- Running well, stable operation since Monday. 1.0l neon, stable at 1120mB. Next will retest empty with empty sequence.
- Level sensors tested and they are working nicely. >100mK change when in vapour. 0mK change in liquid.
- Will check what happens when fans are turned off.
- Progress report JB/PW/MT/HN
- Current technical
- Refurbishment of pipework from turret to wall.
- P.Lester now on the job. OxFab making transfer line. EC and JT will make pipe supports. To be done by next week.
- Will need to survey in situ to calculate length of central section of pipe.
- Refurbishment of pipework from wall to roof and vent.
- Need to inspect work that need to be done.
- Refurbishment of pipework from turret to wall.
- Documentation
- List compiled by AN in OPI and required at final safery tour.
- Operational risk assessments and method statements
- Service and maintenance manuals and/or documents
- List of Competent Persons
- Test certificates and statutory written schemes of inspection and declarations of conformity
- Completed action list from the preliminary safety tour, including actions from technical reviews and HAZOP
- Sign off sheet(s)
- Approval of the liquid hydrogen system by the Liquid Hydrogen Working Group
- List compiled by AN in OPI and required at final safery tour.
- Timetable
- Next meeting
- Thurs 03th August 2017; in the MLCR
- AoB
Summary of actions¶
- CMcW: to trace trigger signal to FC datalogger.
- PW: to modify purge sequence limits in agreement with JB.
- AK/PW: to test permissions of required connections HMI to PLC.
- MT/JB: Ensure D. Haines witnesses test of quench valve and complete appropriate documentation.
- JB: Atex rating of everything in H2 shed.
- JB: to prepare rota on 'limited call-out' basis
- CW: to contact HR re 'on-call' times
Back to LH2:¶
Files:¶
Updated by Long, Kenneth almost 6 years ago · 6 revisions