2017-07-13-LH2¶
6th July 2017; 11:00 BST¶
Notes¶
Actions¶
- Action AK follow through de-bugging of FC datalogger.
- Action CMcW to install NI on MICEnet machine.
- Action MT/JB to agree and implement testing of quench valves.
- Action PW to modify purge sequence limits in agreement with JB.
- Action AK/PW to determine required connections HMI to PLC
• Action JB to post notes from 'GUI' meeting to Wiki
• Action CMcW to search archiver for FC radiation shield temp & helium pressure excursions
• Action JB/MT/CMcW to verify instrumentation. - Action PF to re-instate remote monitoring and control for neon run.
Monitoring and archival of data - PF/AK¶
Current technical¶
- FC pressure rating
- Documentation JT
- Refurbishment of pipework from turret to gas panel and plenum.
- JT released drawings 4/7/17. P Lester to fabricate.
- Quench line support - ?? to design?
- Refurbishment of pipework from plenum to roof and vent
- Swap 2nd sections and cut new holes in shed at higher level to clear obstructions - PL to implement..
- Neon Run
- Shifters- Atex training
Timetable¶
- Next meeting
- AoB