2017-07-06-LH2

6th July 2017; 11:00 BST

Phone details

Notes

Actions

  • Action AK follow through de-bugging of FC datalogger.
  • Action CMcW to install NI on MICEnet machine.
  • Action MT/JB to agree and implement testing of quench valves.
  • Action PW to modify purge sequence limits in agreement with JB.
  • Action MT/JB/AK to agree monitoring GUI, discuss alarm handler and agree archiver PVs
  • Action AK to clarify how HMI is connected to PLC.

Monitoring and archival of data - PF/AK

Current technical

  • FC pressure rating
    • Documentation JT
  • Refurbishment of pipework from turret to gas panel and plenum.
    • JT released drawings 4/7/17. P Lester to fabricate.
    • H2 supply line 'boot' - complete - delivered.
    • Quench line support - ?? to design?
  • Refurbishment of pipework from plenum to roof and vent
    • Swap 2nd sections and cut new holes in shed at higher level to clear obstructions - PL to implement..
  • Neon Run
  • Shifters- Atex training

Timetable

  • Next meeting
  • AoB