Schedule 2016-05-05¶
FNAL propose visit week beginning 24th May 2015¶
Schedule¶
- W/C 2nd May
- Resistors and cabling
- Emergency stops
- W/C 9 May
Into short circuit at Link Box
- Resistors
- E-stop
- interlock verification
- PS Stability - shorts
- W/C 16 May
Into SS Magnets
- Verify QP
- Resistors.
- Finally check power supplies are stable into magnet (<10A), with the inclusion of the additional parallel resistors and that current flows correctly into each coil. (Needs approval from Alan Bross)
- Handover the system for QP system set-up and training.
Updated by Whyte, Colin over 7 years ago ยท 1 revisions