FNAL propose visit week beginning 24th May 2015

Schedule

  • W/C 2nd May
  • Resistors and cabling
  • Emergency stops
  • W/C 9 May

Into short circuit at Link Box

  • Resistors
  • E-stop
  • interlock verification
  • PS Stability - shorts
  • W/C 16 May

Into SS Magnets

  • Verify QP
  • Resistors.
  • Finally check power supplies are stable into magnet (<10A), with the inclusion of the additional parallel resistors and that current flows correctly into each coil. (Needs approval from Alan Bross)
  • Handover the system for QP system set-up and training.