h1. Hall workplan : 27/6/2016 - 1/7/2016
2
3
4 2 Boyd, Steven
* *Monday*
5 1 Boyd, Steven
6
** MOM in charge. (Paulo Francini)
7
** DC On call. (Paul Hodgson)
8
** Hall Locked, controlled access only.
9
** Expert lead run with no beam (pulsar only)
10
** Fully test DAQ, Run Control, Target (raised) and Alarm Handler.
11
** In parallel attempt to fix instability in FCU ramp enable interlock 
12
** (module swap?).
13
14 2 Boyd, Steven
* *Tuesday*
15 1 Boyd, Steven
16
** MOM in charge. (Paulo Francini)
17
** DC On call. (Paul Hodgson)
18
** Hall Locked, limited controlled access.
19
** Magnet review people need hall access 11:00 - 12:00
20
** Morning - Field off data taking possible?
21
** (Early) afternoon - Beam bump/timing adjustment.
22
** MOM - DC handover.
23
** US team (Shandor) arrives.
24
** DL team arrive for final magnet commissioning (SSD and FC).
25
26 2 Boyd, Steven
* *Wednesday*
27 1 Boyd, Steven
28
** DC in charge. (Paul Hodgson)
29
** MOM on call
30
** Priority for SSD commissioning
31
** FC soak test if not already done.
32
33 2 Boyd, Steven
* *Thursday*
34 1 Boyd, Steven
35
** DC in charge. (Paul Hodgson)
36
** SSD commissioning.
37
** Full magnet chain (SSU - FC - SSD) power test(s) but need a formal plan 
38
** for this.
39
40 2 Boyd, Steven
* *Friday*
41 1 Boyd, Steven
42
** DC in charge. (Paul Hodgson)
43
** SSD commissioning.
44
** Full magnet chain (SSU - FC - SSD) power test(s)
45
46
* DC - MOM handover ready for weekend shifts
47
48
* Note.
49
50
*Assumption is that all magnet commissioning is done at this time. Very 
51
probable we will need to continue magnet work into following week.
52
We have 2 shifters for weekend and next week but no BLOC (Henry?).*