Actions
Hall workplan : 27/6/2016 - 1/7/2016¶
- Monday
- MOM in charge. (Paulo Francini)
- DC On call. (Paul Hodgson)
- Hall Locked, controlled access only.
- Expert lead run with no beam (pulsar only)
- Fully test DAQ, Run Control, Target (raised) and Alarm Handler.
- In parallel attempt to fix instability in FCU ramp enable interlock
- (module swap?).
- Tuesday
- MOM in charge. (Paulo Francini)
- DC On call. (Paul Hodgson)
- Hall Locked, limited controlled access.
- Magnet review people need hall access 11:00 - 12:00
- Morning - Field off data taking possible?
- (Early) afternoon - Beam bump/timing adjustment.
- MOM - DC handover.
- US team (Shandor) arrives.
- DL team arrive for final magnet commissioning (SSD and FC).
- Wednesday
- DC in charge. (Paul Hodgson)
- MOM on call
- Priority for SSD commissioning
- FC soak test if not already done.
- Thursday
- DC in charge. (Paul Hodgson)
- SSD commissioning.
- Full magnet chain (SSU - FC - SSD) power test(s) but need a formal plan
- for this.
- Friday
- DC in charge. (Paul Hodgson)
- SSD commissioning.
- Full magnet chain (SSU - FC - SSD) power test(s)
- DC - MOM handover ready for weekend shifts
- Note.
Assumption is that all magnet commissioning is done at this time. Very
probable we will need to continue magnet work into following week.
We have 2 shifters for weekend and next week but no BLOC (Henry?).
Updated by Boyd, Steven over 7 years ago ยท 2 revisions