Hall workplan : 27/6/2016 - 1/7/2016

  • Monday
  • MOM in charge. (Paulo Francini)
  • DC On call. (Paul Hodgson)
  • Hall Locked, controlled access only.
  • Expert lead run with no beam (pulsar only)
  • Fully test DAQ, Run Control, Target (raised) and Alarm Handler.
  • In parallel attempt to fix instability in FCU ramp enable interlock
  • (module swap?).
  • Tuesday
  • MOM in charge. (Paulo Francini)
  • DC On call. (Paul Hodgson)
  • Hall Locked, limited controlled access.
  • Magnet review people need hall access 11:00 - 12:00
  • Morning - Field off data taking possible?
  • (Early) afternoon - Beam bump/timing adjustment.
  • MOM - DC handover.
  • US team (Shandor) arrives.
  • DL team arrive for final magnet commissioning (SSD and FC).
  • Wednesday
  • DC in charge. (Paul Hodgson)
  • MOM on call
  • Priority for SSD commissioning
  • FC soak test if not already done.
  • Thursday
  • DC in charge. (Paul Hodgson)
  • SSD commissioning.
  • Full magnet chain (SSU - FC - SSD) power test(s) but need a formal plan
  • for this.
  • Friday
  • DC in charge. (Paul Hodgson)
  • SSD commissioning.
  • Full magnet chain (SSU - FC - SSD) power test(s)
  • DC - MOM handover ready for weekend shifts
  • Note.

Assumption is that all magnet commissioning is done at this time. Very
probable we will need to continue magnet work into following week.
We have 2 shifters for weekend and next week but no BLOC (Henry?).

Updated by Boyd, Steven over 7 years ago ยท 2 revisions