Web Whiteboard » History » Revision 36
« Previous |
Revision 36/153
(diff)
| Next »
Rogers, Chris, 25 July 2013 10:43
Web Whiteboard for MICE Hall operations¶
- Table of contents
- Web Whiteboard for MICE Hall operations
Here are a list of issues associated with operating the experiment. This should be viewed by the shifter and MOM before calling experts. This is complementary to the whiteboard in the control room.
Access / Construction Work¶
The Hall is clear.
The DSA is shut.
There is currently a big hole in the floor of the North Mezzanine. This has been patched with some plywood awaiting permanent fix.
Crane use in Hall is limited. Contact Hall Manager (Andy Nichols) if you have questions or are in need of the cranes.
Interlocks and Controls¶
The target gate valve is open.
Magnet-On Lamps (beamline magnets) - power supply serviced - system incomplete do not run magnets until tests complete
DS quench system - work imminent
Services (electricity / water / air / air-conditioning / network)¶
No service interuptions scheduled.
DS running - no work on instrument air system allowed!
- Unit 1: Low pressure circuit 1 (24 Jul 13)
- Unit 4: Filter Change Alarm;
- All Units: LAN disconnected alarm
Alarm on water chiller outside MLCR
Systems¶
Decay Solenoid¶
- External He cylinder pack is connected to buffer-tank fill line, with regulator set to 2.5 BarG, and fill-line valves open.
- DS oil webcam not displaying correctly - Victoria Bayliss to fix
- DS pump 1 broken - experts notified
PPS¶
Remedial work needed prior to SC magnets - see #1269
Planned hall activities¶
Chris Rogers | 22-23 July | Hall closed for Shifter training |
Victoria Blackmore | 16:00 2nd - 5th August | Hall closed for data taking |
Jason Tarrant | 22-25 August | Hall access required for return yoke discussion |
ISIS user run dates | 17th September | ISIS user run is now a week earlier at 17th September - see below |
PROVISIONAL as of 24 July ISIS user run is expected to start a week earlier on 17th September. Machine physics will also start a week earlier. Minor maintenance day will be the same. Following cycle (February) will also be a week earlier.
Updated by Rogers, Chris over 10 years ago · 36 revisions