Step 4 Running Requirements

Personnel

Task Sub Task Owner Notes
Pool of MOMs Boyd
Pool of BLOCs Nebrensky ~5 trained at present
Pool of SOCs Rajaram
Pool of shifters Kyberd? 24 at current count, 6 qualified as lead shifters, see Training_Shifters
Shift allocation scheme and recording system Blondel
Detector experts Sub system owners

Muon Beamline

Overall responsibility for beamline rests with Nebrensky.

Task Sub Task Owner Notes
Target Hodgson
Decay Solenoid
Proton Absorbers
Conventional Magnets Hughes
Beam Stop Govans

Cooling Channel

Overall responsibility for cooling channel magnets rests with Pasternak.

Task Sub Task Owner Notes
Spectrometer Solenoids
Hydrogen delivery system Watson
FC1 Cobb
LH2 Absorber
LiH Absorber
Quench Protection and Monitoring

Detectors

Overall responsibility for detectors rests with Soler.

Task Sub Task Owner Notes
CKOVs Cremaldi
TOFs Bonesini
Tracker Adey / Dobbs / Uchida Detailed plan in place, needs integrating with main MICE schedule, see http://micewww.pp.rl.ac.uk/documents/85
KL Tortona
EMR Blondel

Hall and Infrastructure

Task Sub Task Owner Notes
Hall Services
Neutron Monitor
Oxygen depletion alarm
PPS
Clean (what standard?)
Surveys
PRY
Cooler Compressors
Vacuum System
Power Systems

DAQ

Task Sub Task Owner Notes
DATE Karadzhov
Run Control Interface Hanlet
Digitisation boards (-> FPGA system) Karadzhov

Online Computing

Task Sub Task Owner Notes
Online Monitoring
Online Reconstruction
Data storage and movement Nebrensky
UPS
RAID systems
Data mover Nebrensky
Controls and Monitoring Hanlet
Run Control Hanlet
Alarm handler Hanlet
Environment readout Hanlet
Webcams
DS
Target
Proton absorber Hanlet

Offline Computing

Task Sub Task Owner Notes
Full reconstruction chain with all detectors
Global fits
Data quality checks
Automated grid batch processing