Step4RunningRequirements » History » Version 27
Dobbs, Adam, 07 May 2014 13:49
1 | 2 | Dobbs, Adam | h1. Step 4 Running Requirements |
---|---|---|---|
2 | 1 | Dobbs, Adam | |
3 | 23 | Dobbs, Adam | {{toc}} |
4 | |||
5 | 1 | Dobbs, Adam | h2. Personnel |
6 | |||
7 | 15 | Dobbs, Adam | | |
8 | 21 | Dobbs, Adam | | *Task* | *Sub Task* | *Owner* | *Notes* | |
9 | 24 | Dobbs, Adam | | Pool of MOMs | | Boyd | | |
10 | | Pool of BLOCs | | Nebrensky | ~5 trained at present | |
||
11 | | Pool of SOCs | | Rajaram | | |
||
12 | | Pool of shifters | | Kyberd? | 24 at current count, 6 qualified as lead shifters, see [[Training_Shifters]] | |
||
13 | | Shift allocation scheme and recording system | | Blondel | | |
||
14 | | Detector experts | | Soler | | |
||
15 | 15 | Dobbs, Adam | | |
16 | 1 | Dobbs, Adam | |
17 | h2. Beamline |
||
18 | |||
19 | 19 | Dobbs, Adam | Overall responsibility for beamline rests with Pasternak / Nebrensky. |
20 | |||
21 | 16 | Dobbs, Adam | | |
22 | 21 | Dobbs, Adam | | *Task* | *Sub Task* | *Owner* | *Notes* | |
23 | 22 | Dobbs, Adam | | Target || Hodgson | |
24 | | Decay Solenoid | | | | |
||
25 | | Proton Absorbers | | | | |
||
26 | | Conventional Magnets | | Hughes | | |
||
27 | | Beam Stop | | Govans | | |
||
28 | 16 | Dobbs, Adam | | |
29 | 1 | Dobbs, Adam | |
30 | 6 | Gamet, Raymond | h2. Cooling Channel |
31 | 1 | Dobbs, Adam | |
32 | 18 | Dobbs, Adam | | |
33 | 21 | Dobbs, Adam | | *Task* | *Sub Task* | *Owner* | *Notes* | |
34 | | Spectrometer Solenoids | | | | |
||
35 | | Hydrogen delivery system | | Watson | | |
||
36 | | FC1 | | Cobb | | |
||
37 | | LH2 Absorber | | | | |
||
38 | | LiH Absorber | | | | |
||
39 | | Quench Protection and Monitoring | | | | |
||
40 | 18 | Dobbs, Adam | | |
41 | 7 | Gamet, Raymond | |
42 | h2. Detectors |
||
43 | 6 | Gamet, Raymond | |
44 | 18 | Dobbs, Adam | | |
45 | 21 | Dobbs, Adam | | *Task* | *Sub Task* | *Owner* | *Notes* | |
46 | | CKOVs | | Cremaldi | | |
||
47 | | TOFs | | Bonesini | | |
||
48 | | Tracker | | Adey / Dobbs / Uchida | Detailed plan in place, needs integrating with main MICE schedule, see http://micewww.pp.rl.ac.uk/documents/85 | |
||
49 | | KL | | Bogolimov | | |
||
50 | | EMR | | Blondel | | |
||
51 | 18 | Dobbs, Adam | | |
52 | 1 | Dobbs, Adam | |
53 | 6 | Gamet, Raymond | h2. Hall and Infrastructure |
54 | 1 | Dobbs, Adam | |
55 | 25 | Dobbs, Adam | | |
56 | | *Task* | *Sub Task* | *Owner* | *Notes* | |
||
57 | | Hall Services | | | | |
||
58 | | | Neutron Monitor | | | |
||
59 | | | Oxygen depletion alarm | | | |
||
60 | | | PPS | | | |
||
61 | | | Clean (what standard?) | | | |
||
62 | | | Surveys | | | |
||
63 | 26 | Dobbs, Adam | | PRY | | | | |
64 | | Cooler Compressors | | | | |
||
65 | | Vacuum System | | | | |
||
66 | | Power Systems | | | | |
||
67 | 27 | Dobbs, Adam | | |
68 | 5 | Dobbs, Adam | |
69 | h2. DAQ |
||
70 | 1 | Dobbs, Adam | |
71 | * DATE |
||
72 | * Run Control Interface |
||
73 | * Digitisation boards (-> FPGA system) |
||
74 | |||
75 | h2. Online Computing |
||
76 | |||
77 | 6 | Gamet, Raymond | * Online Monitoring |
78 | * Online Reconstruction |
||
79 | 1 | Dobbs, Adam | * Data storage and movement |
80 | 9 | Gamet, Raymond | |
81 | * UPS |
||
82 | 6 | Gamet, Raymond | * RAID systems |
83 | * Data mover |
||
84 | * Controls and Monitoring |
||
85 | 10 | Gamet, Raymond | |
86 | 6 | Gamet, Raymond | * Run Control |
87 | * Alarm handler |
||
88 | * Environment readout |
||
89 | * Webcams |
||
90 | * DS |
||
91 | * Target |
||
92 | * Proton absorber |
||
93 | 1 | Dobbs, Adam | |
94 | |||
95 | h2. Offline Computing |
||
96 | |||
97 | * Full reconstruction chain with all detectors |
||
98 | * Global fits |
||