Step 4 Readiness (summer 2016) for MDR7¶
Raw list includes some things marked as already done as they need re-doing (e.g. new unpacking including Hall probes) and a lot of repetition (and some items may even be done already).
List of issues at summer 2016, culled from
Step 4 Requirements
24 June Readiness Meeting
28 June Operations Meeting and issues from MDR7
21 June Operations Meeting
14 June Operations Meeting
7 June Operations Meeting
February 2016 List
Beamline (c.f. #1854 )¶
Target- Target Alarm handler #1613 update 22 (CAM)
- ISIS data items #1669 (CAM)
- Activation Study (activation seen: limit of 2 V at MS/64 stands)
Beambump tune- Updated target manual (EO/JL)
- Updated target checklists (Henry)
review existing water flows and temperature range (MBC)- need limit in control software? (CAM)
- Calibrate D1 & D2 current reading and update IOC software (DL)
Q1 MPS start-up recalcitrance (DL)Q1 MPS replaced- Replaced the PS. Does it have correct polarity?
- Q1 alarm on voltage at zero amps (CAM)
- Q4 oscillation below 10A and anomalous ramp rate (DL)
- Trench water leak / Q5 water leak : Q5 has been fixed.
- Q6 leak : too fragile, wouldn't touch it - shifters to watch
- Leak sensors and drip trays
- Water, temperatures and MPS water flows in ALH (CAM)
*Q6 temperature alarm limits missing!*
- DS readback current requires calibration (DL)
- Overheating investigation (DK/DL)
- Calibrate current reading and update IOC software (DL)
- 120A trip investigation (DK/DL)
- Replace final battery cell (DL - confirmed still outstanding )
- Diodes in BBU circuit (DL)
- Boosted air (MBC)
Trench sensor(awaiting read-out)- Compressor sensor
- Backup compressor for DS
- Linde PC install: awaiting validation and IOC (DK) - licence issues
- DS ALH/archiver corrections #1710 (CAM)
- DS Fridge instability : Has been investigated by Mark. Monitor.
- Proton absorber sticking : Hasn't been reproduced lately - shifters will need to monitor it.
- BLOC training and experience (MBC)
- BLOC roster
- Put BLOCs in CHEESE (Steve) : Done
Detectors, Monitoring and Control¶
- Tracker leak (Melissa/Tracker group)
- GVA1 status (???) -- Durga/John N. to look at effect on beamline -- Removed: (no longer) in geometry?
- CKOV monitoring : Should now be operational. Will be checked at expert run (actually, I think it was the KL monitor).
- HV channels (?) : Some HV channels are reporting as -1 in the 527. Check at expert run.
- MDR7: SY527 issues
- MDR7: TOF2: current trip in TOF2_103
- Get Helium flushing the tracker now (John)
- Need a procedure for the MOM to check the Helium level for the tracker to know when to change the bottle (John)
- Monitoring GUI for the tracker volumes needs to be added in the AppLauncher
- issue with the EMR DAQ (restarted the crate)
- CDB vs Spreadsheet (All) -- resolved to remove spreadsheet by end of user run
- Alarm Handlers and State Machines
- Go over FC and DS alarm handler spreadsheets (Pierrick,Mark,John C)
- Expert panel readiness : Done
- Feedback from OnMon to RC to tell ALH that data has become corrupted. #1802 (Rhys, Pierrick)
- SSH lockout procedure documentation (Paolo) and details of implementation (Steve)
- Test of network reconfiguration (Pierrick, Paolo)
- Devising a way to record the absorber details in the CDB (Pierrick, Durga)
- Confirm ISIS PVs and applications OK in MLCR (Ops)
- Check that PRY movement monitor measurements are in the archiver (Pierrick) : Stands
Cooling Channel¶
- "Commissioning Manager" and planning of that process
- RA, Operating Instructions, etc.
- Progress on SS procedure documentation
- Install FC monitoring in ISIS MCR (Pierrick,Paolo)
- Hall probe communication problems
- John G to think about a shielding solution for the Hall probe connectors
- There needs to be someone on call for the SC magnets. It will be a combination between Josef/Mark
Hall and infrastructure¶
- Cooling water system
- PID alignment and survey
- PPS issues #1818 ?
- Fencing under South Mezzanine
- All valid PPS meshing and gates in place
- camhall03 inverted
- Neutron Monitor remote readout
- Shared services/environment (water, air, computing/networking, UPS ( #1213 ) in Alarm Handler and in Archiver (CAM)
- Water fail document
- Additional ambient air temperature sensors
- Post-MDR7: Aircon unit assignment incorrect in monitoring GUI
General Computing¶
- DATE/OnMon/OnRec error messages all need timestamps, to allow correlation* Data Quality Flags #1383 (All, Janusz, Pierrick)
- DATE crash on first run of the day : Done? (fix actually deployed?)
- Data Quality Flags #1383
- Reco: Data Quality flags #1585 (Rhys, Durga, Pierrick)
- onrec disk full - cron in place?
- miceraid5 disk full : Paolo has updated Nagios so it will keep an eye on this. We are down to 250 GB so we should do a preemptive cleanup. Get in touch with Yordan on self-cleanup.
CDB : do we have all necessary information in the CDB- Get Target Depth, Target Delay, Total Beam Loss to read out (currently 0 or blank) - not appropriate for CDB?
- Solenoid currents
- Solenoid polarity
- Focus coil current
- Focus coil polarity
- Absorber material
- Absorber pressure (if necessary)
- Tracker gas and pressure
- MDR7: issue writing in the CDB the new tables
- CDB viewer needs to have the cooling channel magnets and absorber status. Action : Janusz
- Implement a search function for the CDB (Someone)
- File Compactor:
- Alarm Handler #1236
- Data Quality Flags #1383 (Henry, Pierrick)
- Compactor file corruption : Looks like two processes were running simultaneously which shouldn't happen.
- MDR7: Data mover issue after the re-installation of miceonrec01: SOLVED and TESTED
- Automated RECO mover:
- Automated mover and concentrator running
- RECO-robot on hardware token
Formal freeze of online software : Monday 27th June- Access to EPICS archiver over the net (Cobb)
- Nagios/Heart beat alarms : Done (who gets notified, and when?)
- Backups not working for a fortnight : Refer to Paolo to see if we need an alarm for backups.
Operations¶
- Address values of the alarm limits (Steve, Paul H)
- What are SS settings for reference runs (All) : Decide to continue use current conventional magnet reference settings regardless of the SS currents
- Run 7851 - what happened and has the mess been fixed?
- Padlock-able overnight keypress -- in progress
- Start working through Hall prep list
- SC Controlled Entry procedure (mezzanine access, ODH, et al.)
- Ensure up-to-date documentation and checklists in MLCR:
- Experts to review documentation and training needs during MDR7
- especially Control Room Operations which is incomplete and out of date
- need Alarm Handler training (screenshots, etc.?) and File Compactor
- Update operations checklist
- All shifter documentation up-to-date (???) and in MLCR binders (Boyd)
- Shift checklist update : suggestions
- Emergency procedures and documentation for shifters and experts
- Expert list
- Procedure whilst control room is unmanned : CC kept energised with MCR oversight.
- Experts to review documentation and training needs during MDR7
- Training plan : http://micewww.pp.rl.ac.uk/projects/operations/wiki/TrainingPlan201602
- New elements
- Whatever is needed for the SS and FC
- Alarm Handler
- PPS Door lock (bouncing) : train people not to bang doors.
- New elements
Shifter Roster- Shifters skipping training
- Same shifters due this cycle
- Sick shifters (?) : Don't come in if dying. Tell MOM if sick. remind third-parties
- Permissive list of MOM-authorisable actions -- in progress
- Tidy up MLCR
Issue | Responsible Party | System | Issue Description | Data Noted | Status | Date Completed |
MDR1-DET-05 | M.Uchida | Tracker | Sufficient spares for the tracker readout should be commissioned so that they are hot-swappable | 2015-01-21 | In progress | |
MDR1-DET-06 | M.Uchida | Tracker | The tracker cryogenics temperature fine control should be repaired | 2015-01-21 | ||
MDR1-DET-10 | M.Uchida | Tracker | The tracker internal and external LED systems should be made operational | 2015-01-21 | ||
|
Y.Karadzhov | DATE | A new unpacking should be released to online monitoring and online reconstruction developers | 2015-01-21 | 2016: Hall probe readout | |
MDR1-DAQ-03 | Y.Karadzhov | DATE | The crashes in the InfoBrowser should be understood and fixed. This is the principal tool for DAQ debugging and is needed for both shifters and experts | 2015-01-21 | ||
MDR1-CAM-03 | P.Hanlet | EMR | Remote operation of the EMR should be established | 2015-01-21 | In progress | |
MDR1-CAM-04 | M.Uchida | Tracker | Remote operation of the tracker should be integrated with the rest of the controls software | 2015-01-21 | In progress | |
MDR1-CAM-05 | P.Hanlet | Diffuser | The "diffuser set" indicator should be fixed in the diffuser controls GUI | 2015-01-21 | In progress | |
MDR1-CAM-11 | P.Hanlet | RunControl | Add buttons to Arm/Start/Pause/Stop DATE | 2015-01-21 | Near completion; still needs lock files | |
MDR1-CAM-12 | P.Hanlet | RunControl | Consider adding Online Monitoring and Online Reconstruction notifications #1802 | 2015-01-21 | In progress | |
MDR1-CAM-13 | P.Hanlet | RunControl | Confirm configuration write to CDB after first trigger, Begin/End run comments and tag run | 2015-01-21 | Requires beam | |
MDR1-CAM-14 | P.Hanlet | Target | Add target optical readouts to Alarm Handler | 2015-01-21 | Awaiting Matt's fixing PV updating | |
|
A.Dobbs | MAUS | A new version of MAUS should be installed (released?) when an updated DAQ unpacking becomes available | 2015-01-21 | 2016: Hall probe readout | |
MDR1-CMP-05 | J.Martyniak | CDB | The Configuration Database get_tagged_beamline read should be fixed | 2015-01-21 |