Project

General

Profile

Actions

ShifterTrainingTarget » History » Revision 4

« Previous | Revision 4/12 (diff) | Next »
Nebrensky, Henry, 07 April 2015 16:02
RATS daemon crash


Shifter Training Syllabus for the Target (Spring 2015)

  1. Starting the relevant control screens
  2. Start/Stop Actuation
  3. ISIS beamloss and target depth adjustment
  4. Pausing target operations: stop, withdraw, start, go deeper
  5. Raise and lower frame
  6. Controlled Entry: stop, withdraw, raise frame, lower frame, start, go deeper
  7. Overnight Standby: stop, withdraw, raise frame, park, brass key, hold, test, lower frame, start, go deeper
  8. RF Hall (R5.4) access and the Target Frame Enable key
  9. Errors and BPS Trip procedure
    • RATS daemon crash symptoms

Updated by Nebrensky, Henry over 8 years ago · 4 revisions