Shifter Training Syllabus for the Target (Spring 2015)

  1. Start/Stop Actuation
  2. ISIS beamloss and target depth adjustment
  3. Pausing target operations: stop, withdraw, start, go deeper
  4. Raise and lower frame
  5. Controlled Entry: stop, withdraw, raise frame, lower frame, start, go deeper
  6. Overnight Standby: stop, withdraw, raise frame, park, brass key, hold, test, lower frame, start, go deeper
  7. RF Hall (R5.4) access and the Target Frame Enable key
  8. BPS Trip procedure