Shifter Training Syllabus for the Target (Spring 2015)

  1. Starting the relevant control screens: RATS, (shifter) Target Drive, ISIS Beam Loss Display
    1. RATS: bookmarked in Firefox
    2. Target Drive
      Expert Target Drive Panel
    3. ISIS Beam Loss Display
      ISIS Beam Loss Display
  2. Start/Stop Actuation
  3. ISIS beamloss and target depth adjustment
  4. Pausing target operations: stop, withdraw, start, go deeper
  5. Raise and lower frame
  6. Controlled Entry: stop, withdraw, raise frame, lower frame, start, go deeper
  7. Overnight Standby: stop, withdraw, raise frame, park, brass key, hold, test, lower frame, start, go deeper
  8. Vac-Rack and the Target Frame Enable key - NB requirement for a priori RF Hall (R5.4) swipe access
  9. Errors and BPS Trip procedure