Hall Preparation List¶
Preparation for each running period (data-taking campaign)¶
- Schedule updated surveys if equipment has been moved [**] 2 months before running
- Make a request to ISIS for data taking (*1 week before running)*
- Check Hall air-conditioning units all work
- Check beamline polarity and get it changed if needed
- Check POMPOM voltage and make sure is correct at 12 V
- Check ISIS PVs and software applications still work 2 weeks before running
- Check DS turret fan is running [**]
- Check PPS doors/BOBs OK
- Check target frame movement
- Turn on SY527 and SY127 HV supplies
- Cranes moved to West end of Hall (away from ISIS)
- Erect temporary fencing around Q789/TOF1, around TOF2/KL, and across gap by sliding floors
- Paperwork
- Authorization to Work (ATWs) in Collaboration with Andy Nichols
N.B. Items ** may need DSA or ISIS access to rectify any problems
Higher level tasks¶
- Run up all beamline magnets
- While magnets are ON - make visual inspection of Magnet-ON lights located on each beamline magnet
- Test target (dipping and frame movement)
- make sure DAQ works (e.g. takes cosmic data) and is in a sensible configuration (selection of spill gate/trigger condition/event buffer etc.)