RunPlan20170227 » History » Revision 27

« Previous | Revision 27/38 (diff) | Next »
Rajaram, Durga, 06 March 2017 11:51


Run Plan 27/02/2017 - next change of CC currents

Feb. 27 - Mar. 6

Date Feb 27 Feb 28 Mar 1 Mar 2 Mar 3 Mar 4 Mar 5 Mar 6
MOM M. Uchida M. Uchida M. Uchida M. Uchida M. Uchida M. Uchida M. Uchida M. Uchida
BLOC J. Langlands Y.Song Y.Song Y.Song Y.Song Y.Song
SOC D. Rajaram D. Rajaram D. Rajaram D. Rajaram D. Rajaram D. Rajaram D. Rajaram D. Rajaram
Lead Shifter(08:00-16:00) S. Wilbur S. Wilbur S.Wilbur A. Blondel A. Blondel A. Blondel A. Blondel A. Blondel
shifter 2 (08:00-16:00) M.Federova M.Federova M.Federova P. Kyberd P. Kyberd S. Boyd S. Boyd P. Franchini
Lead shifter (16:00-00:00) J. Martyniak D. Rajaram D. Rajaram Y.Song Y.Song Y.Song Y.Song Y.Song
Shifter 2 (16:00-00:00) M.Savic M.Savic M.Savic A. Bross A. Bross A. Bross A. Bross A. Bross
Lead Shifter (00:00-08:00) E.Overton V. Bayliss C. Rogers M.Federova D. Rajaram Durga -Tanaz Ken-Tanaz M. Courthold
Shifter (00:00-08:00) M.Bogomilov M.Bogomilov M.Bogomilov M.Bogomilov M.Bogomilov M.Bogomilov
Additional Personnel
Notes

Data to take

Field on data

Take H16a data until complete then H16b until complete then if time before 3pm H16c. After magnet ramp straight track data (alignment scan),

Momentum Scan

Task Momentum # Tof2 Triggers Beamline Tag CoolingChannel Tag Similar runs Final Event Tally (k)
H16a 240 200K TOF2 DiffMask8-3-240+M3-Test1 2016-05-2
H16b 200 200K TOF2 DiffMask8-3-200+M3-Test1 2016-05-2
H16c 170 200K TOF2 DiffMask8-3-170+M3-Test2 2016-05-2

Straight track data

Detector alignment

Task Momentum # Particle Triggers Beamline Tag ColingChannel Tag Similar runs Final Event Tally (k)
S7b 300 1000k at TOF1 DiffMask8... StepIV-Off 8030
S7c 400 1000k at TOF1 DiffMask8...400MeV+pi pa82 StepIV-Off 8041

TOF calibration

Task Momentum # Particle Triggers Beamline Tag CoolingChannel Tag Final Event Tally (k)
S8a 150 2M @ TOF1 DiffMask8...ToF-Calib+150 StepIV-Off
S8b 300 1M @ TOF1 DiffMask8...ToF-Calib+300 StepIV-Off

Finished / Part complete Runs

Emittance reduction DONE

Task Momentum # Tof2 Triggers Beamline Tag CoolingChannel Tag Similar runs Final Event Tally (k)
H15a 140 600K TOF2 DiffMask8-3-140+M3-Test4 2016-05-2 1.545e6
H15b 140 600K TOF2 10-140+M3-Test3 2016-05-2 1.4e6

Detector alignment PART DONE

Task Momentum # Particle Triggers Beamline Tag ColingChannel Tag Similar runs Final Event Tally (k) @ 10am
S5b 300 1000k at TOF1 300MeV+pi pa82 StepIV-Off 8030 400
S5c 400 1000k at TOF1 400MeV+pi pa82 StepIV-Off 8041

TOF calibration PART DONE

Task Momentum # Particle Triggers Beamline Tag CoolingChannel Tag Final Event Tally (k) @ 10am
S6a 150 2M @ TOF1 ToF-Calib+150 StepIV-Off 448
S6b 300 1M @ TOF1 ToF-Calib+300 StepIV-Off 220

After next magnet ramp Not done!!

Task Momentum # Tof2 Triggers Beamline Tag CoolingChannel Tag Similar runs Final Event Tally (k)
H17a 200 600K TOF2 DiffMask8-3-140+M3-TSpecial Run 2016-05-3
H17b 200 600K TOF2 10-140+M3-Test3 2016-05-3

Spreadsheet: http://micewww.pp.rl.ac.uk/attachments/8315/MICE_User_Run_2016_05-v4a.xls
Performance plots: http://micewww.pp.rl.ac.uk/attachments/8312/plots-v4_50k.tar.gz

Updated by Rajaram, Durga over 6 years ago · 27 revisions