Issues and tasks:

  • beam bump needs to be redone (Monday)
  • roof chiller intervention (Monday)
  • EMR daq stability
  • EMR spare board
  • AMI controller swap (Monday)
  • magnetic sweep need to be renewed
  • diffuser test @ 50A

Daily Preparations Schedules for Running.

Friday 10th:

Ramp DS to 200A.
Fill SSU helium
Check helium level monitor okay
Check trench water and target test, Henry
Lock up hall ready for Saturday

Saturday 11th Expert Run:

  • beam bump tuning - Hayley (ISIS) - DONE
  • straight track data to test all systems - Need to restart and test EMR
  • Tracker startup from 9am - Mismatch in DAQ events to Trigger, Monday
    File Compactor script error detection
    Target tests from 10am
  • Network isolation test, disconnect optical fibre cable on main switch, isolating miceNet from external network (normal data taking activities should not be affected). 30 mins. - TBD

Sunday 12th No work planned

Monday 13th

  • Watchdog error fix
  • Left over from Saturday.

Tuesday 14th

  • Cooling channel magnet ramp

Wednesday 15th

  • Ramping of the CC quench

Thursday 16

  • ramp of SSU (magnet team) - postponed
  • diffuser test (BLOC) - postponed
  • beam bump (Henry liaising with ISIS)
  • tracker calibration (Ed) - DONE
  • beam line tuning (Ao) - postponed
  • eventually straight tracks settings (alignment, calibration)

Friday 17

  • He refill in FC and SSD - DONE
  • beam bump - DONE (to be redone on Monday)
  • straight tracks: S5b

Sunday 18

  • 10A test on SSU and SSD - DONE
  • TOF calibration: S6a, S6b

Wednesday 22

  • Tracker calibration
  • Reference run
  • Momentum scan with SSU on (205A), SSD on (205A), FDC off:
    • Cycle through H17a, H17b, H17c, H17d

Feb 15th to March 6th

Date Feb 15 Feb 16 Feb 17 Feb 18 Feb 19
MOM P. Franchini P. Franchini P. Franchini P. Franchini P. Franchini
BLOC H. Nebrenski T. Mohayai T. Mohayai T. Mohayai T. Mohayai
SOC D. Rajaram D. Rajaram D. Rajaram D. Rajaram D. Rajaram
Lead Shifter (00:00-08:00) D. Maletic D. Maletic D.Maletic D.Maletic D.Maletic
Shifter (00:00-08:00) D. Bowring D. Bowring D.Bowring D.Bowring D.Bowring
Lead shifter (08:00-16:00) T. Mohayai T. Mohayai T. Mohayai T. Mohayai T. Mohayai
Shifter 2 (08:00-16:00) A. DeBari A. DeBari A. DeBari A. DeBari A. DeBari
Lead shifter (16:00-00:00) D. Neuffer D. Neuffer D.Neuffer D.Neuffer D.Neuffer
Shifter 2 (16:00-00:00) A. Liu A. Liu A. Liu A. Liu A. Liu
Additional Personnel
Notes
Date Feb 20 Feb 21 Feb 22 Feb 23 Feb 24 Feb 25 Feb 26
MOM P. Franchini P. Franchini P. Franchini P. Franchini P. Franchini P. Franchini P. Franchini
BLOC Y.Song Y.Song Y.Song Y.Song Y.Song S. Boyd S. Boyd
SOC D. Rajaram D. Rajaram D. Rajaram D. Rajaram D. Rajaram D. Rajaram D. Rajaram
Lead Shifter (00:00-08:00) Y.Song Y.Song Y.Song Y.Song Y.Song E.Overton E.Overton
Shifter (00:00-08:00) C. Rogers M Courthold V. Bayliss E.Overton E.Overton
Lead Shifter(08:00-16:00) D. Rajaram D. Rajaram D. Rajaram D. Rajaram D. Rajaram S. Wilbur S.Wilbur
shifter 2 (08:00-16:00) H. Nebrenski H. Nebrenski H. Nebrenski H. Nebrenski H. Nebrenski M.Federova M.Federova
Lead shifter (16:00-00:00) A. Dobbs A. Dobbs A. Dobbs A. Dobbs A. Dobbs Y. Martyniak Y. Martyniak
Shifter 2 (16:00-00:00) K. Long K. Long K. Long K. Long K. Long M.Savic M. Savic
Additional Personnel
Notes
Date Feb 27 Feb 28 Mar 1 Mar 2 Mar 3 Mar 4 Mar 5 Mar 6
MOM M. Uchida M. Uchida M. Uchida M. Uchida M. Uchida M. Uchida M. Uchida M. Uchida
BLOC Y.Song Y.Song Y.Song Y.Song Y.Song
SOC D. Rajaram D. Rajaram D. Rajaram D. Rajaram D. Rajaram D. Rajaram D. Rajaram D. Rajaram
Lead Shifter (00:00-08:00) E.Overton V. Bayliss C. Rogers
Shifter (00:00-08:00) M.Bogomilov M.Bogomilov M.Bogomilov M.Bogomilov M.Bogomilov
Lead Shifter(08:00-16:00) S. Wilbur S. Wilbur S.Wilbur A. Blondel A. Blondel A. Blondel A. Blondel A. Blondel
shifter 2 (08:00-16:00) M.Federova M.Federova M.Federova P. Kyberd P. Kyberd S. Boyd S. Boyd S. Boyd
Lead shifter (16:00-00:00) J. Martyniak D. Rajaram D. Rajaram Y.Song Y.Song Y.Song Y.Song Y.Song
Shifter 2 (16:00-00:00) M.Savic M.Savic M.Savic A. Bross A. Bross A. Bross A. Bross A. Bross
Additional Personnel
Notes

Data to take:

Field On Data

  • Take all H13a then all H14a-c then H13b then H13c (so that diffuser settings are used last).

Task H13 - Emittance Reduction

Task Momentum # Particle Triggers Beamline Tag CoolingChannel Tag Similar runs Final Event Tally (k)
H13a 140 630K TOF2 3-140+M3-Test2 2016-05-4

Task H14 - Magnet alignment

Task Momentum # Particle Triggers Beamline Tag CoolingChannel Tag Similar runs Final Event Tally (k)
H14a 170 1.5e5 TOF1 3-170+M3-Test1 2016-05-4
H14b 200 1.5e5 TOF1 3-200+M3-Test1 2016-05-4
H14c 240 1.5e5 TOF1 3-240+M3-Test1 2016-05-4

Task H13 - Emittance Reduction with diffuser (after H13a and H14 are completed)

Task Momentum # Particle Triggers Beamline Tag CoolingChannel Tag Similar runs Final Event Tally (k)
H13b 140 315K TOF2 6-140+M3-Test2 2016-05-4
H13c 140 200K TOF2 10-140+M3-Test3 2016-05-4

Data to take after changing the CC settings:

Task H15 - Emittance Reduction

Task Momentum # Tof2 Triggers Beamline Tag CoolingChannel Tag Similar runs Final Event Tally (k)
H15a 140 630K TOF2 3-140+M3-Test2 2016-05-1
H15b 140 315K TOF2 6-140+M3-Test2 2016-05-1
H15c 140 200K TOF2 10-140+M3-Test3 2016-05-1

Task H16 - Magnet alignment

Task Momentum # Particles Triggers Beamline Tag CoolingChannel Tag Similar runs Final Event Tally (k)
H16a 170 5e5 TOF1 3-170+M3-Test1
H16b 200 5e5 TOF1 3-200+M3-Test1
H16c 240 5e5 TOF1 3-240+M3-Test1

Straight track data (fallback)

Detector alignment

Task Momentum # Particle Triggers Beamline Tag ColingChannel Tag Similar runs Final Event Tally (k) @ 10am
S5b 300 1000k at TOF1 300MeV+pi pa82 StepIV-Off 8030 400
S5c 400 1000k at TOF1 400MeV+pi pa82 StepIV-Off 8041

TOF calibration

Task Momentum # Particle Triggers Beamline Tag CoolingChannel Tag Final Event Tally (k) @ 10am
S6a 150 2M @ TOF1 ToF-Calib+150 StepIV-Off 448
S6b 300 1M @ TOF1 ToF-Calib+300 StepIV-Off 220

Step4_Pionic_beam_Tags