h1. RunPlan20161128 to Dec 16th 2016 

 Scattering data with field, backup plan for straight tracks. 

 h3. Daily schedule from 28/Nov to 3/Dec. 

 We expect to be running with 2V beamloss. Note Decay Solenoid is ON. ISIS is at 40+10 and 700 MeV 

 Note:  


 | Date                           | Nov 28          |    Nov. 29          |    Nov. 30          |    Dec. 1          |    Dec. 2           |    Dec. 3          |  
 | MOM                            | E. Overton      |    M. Uchida        |    M. Uchida        |    M. Uchida       |     M. Uchida       |    M. Uchida       | 
 | BLOC                           | Y.Song          |    Y.Song           |    Y.Song           |    Y.Song          |     Y.Song          |    R.Game          | 
 | SOC                            | D. Ragaram      |    D. Ragaram       |    D. Ragaram       |    D. Ragaram      |     D. Ragaram      |    D. Ragaram      | 
 | shifter 2 (08:00-16:00)        | Y.Song          |    Y.Song           |    Y.Song           |    Y.Song          |     Y.Song          |    D.Bowring       | 
 | Lead Shifter(08:00-16:00)      | P. Franchini    |    P. Franchini     |    P. Franchini     |    P. Franchini    |     P. Franchini    |    R.Gamet         | 
 | Lead shifter (16:00-00:00)     | D. Ragaram      |    D. Ragaram       |    D. Ragaram       |    D. Ragaram      |     D. Ragaram      |    P.Soler         | 
 | Shifter 2    (16:00-00:00)       | B.Freemire      |    B.Freemire       |    B.Freemire       |    B.Freemire      |     B.Freemire      |    D.Maletic       | 
 | Lead Shifter    (00:00-08:00)    | G. Vankova      | G. Vankova        |    G. Vankova       |    G. Vankova      |     G. Vankova      |B.Freemire 12-4 | 
 | Shifter          (00:00-08:00) | J. Langlands    | J. Langlands      |    J. Langlands     |    J. Langlands    |     J. Langlands    |    P.Hanlet 4-8    | 
 | Additional Personnel           |                 |                   |                   |                  |                   |                  | 
 | Notes                          |                 Morning training |                |                   |                  |                   |                  | 
 |                             |    Morning Magnet ramp |                |                   |                  |                   |                  | 


 | Date                           | Dec 4           |    Dec. 5           |    Dec. 6           |    Dec. 7          |    Dec. 8           |    Dec. 9         |   
 | MOM                            | M. Uchida       |    M. Uchida        |    M. Uchida        |    M. Uchida       |     M. Uchida       |    M. Uchida      | 
 | BLOC                           | R.Game          |    R.Game           |    R.Game           |    R.Game          |     J.Greis         |    J.Greis        | 
 | SOC                            | D. Ragaram      |    D. Ragaram       |    D. Ragaram       |    D. Ragaram      |     D. Ragaram      |    D. Ragaram     | 
 | Lead shifter (08:00-16:00)     | R.Gamet         |    R.Gamet          |    R.Gamet          |    R.Gamet         |     S.Wilbur        |    S.Wilbur       | 
 | Shifter 2    (08:00-16:00)       | D.Bowring       |    D.Bowring        |    D.Bowring        |    D.Bowring       |     J.Greis         |    J.Greis        | 
 | Lead shifter (16:00-00:00)     | P.Soler         |    P.Soler          |    P.Soler          |    P.Soler         |     D.Neuffer       |    D.Neuffer      | 
 | Shifter 2    (16:00-00:00)       | D.Maletic       |    D.Maletic        |    D.Maletic        |    D.Maletic       |     D.Maletic       |    D.Maletic      | 
 | Lead Shifter    (00:00-08:00)    | M.Courthold     |    M.Courthold      |    P.Kyberd         |    P.Kyberd        |     A.Bross         |    A.Bross        | 
 | Shifter          (00:00-08:00) | B.Freemrire     |    B.Freemrire      |                   |                  |     B.Freemrire     |    B.Freemrire    | 
 | Additional Personnel           |                 |                   |                   |                  |                   |                 | 
 | Notes                          | Morning training |                |                   |                  |                   |                 | 
 |                             |    Morning Magnet ramp |                |                   |                  |                   |                 | 

 h3. Plan for 28/Nov-29/Nov: 

 Do 2 hours of each H4 task, then each H5 task until complete. 

 h1. Data to take 

 Goal: Take some useful data for the experiment. We have two possible scenarios, we have magnets, or we don't. The request list for each scenario is below.. 

 h2. Field On Data 

 Do 2 hours of each H4 task, then each H5 task until complete. 

 h4. Task H4 - Emittance Reduction!! 

 | *Task*     | *Momentum* | *# Triggers*     | *Beamline Tag*        |    *CoolingChannel Tag*    | *Similar runs*     | 
 | H4a         |     140        |     1e6 TOF1       |        3-140+M3-Test2     |       2016-04-01.2     |                  | 
 | H4b         |     140        |     1e6 TOF1       |        6-140+M3-Test2    |       2016-04-01.2     |                  | 
 | H4c         |     140        |     2e6 TOF1       |        10-140+M3-Test3    |       2016-04-01.2     |                  | 

 h4. Task H5 - Magnet alignment 

 | *Task*     | *Momentum* | *# Triggers*     | *Beamline Tag*        |    *CoolingChannel Tag*    | *Similar runs*     | 
 | H5a         |     170        |     5e5 TOF1       |      3-170+M3-Test1     |       2016-04-01.2     |                  | 
 | H5b         |     200        |     5e5 TOF1      |      3-200+M3_Test1 |       2016-04-01.2     |                  | 
 | H5c         |     240        |     5e5 TOF1       |      3-240+M3_Test1    |       2016-04-01.2     |                  | 


 h2. Straight track data (fallback) 

 h3. Task S2: LiH scattering data. 

 | *Task*      | *Momentum* | *# Triggers*     | Beamline Tag         | CoolingChannel Tag    | Similar runs     | 
 | S2a         |     140        |    1M     @ TOF2     |    3-140+M3-Test2      |                      |                  | 
 | S2b         |     200        |    ?               |        6-200+M0        |                      |                  | 

 Task S2a - 10M triggers at TOF1, 33 triggers/spill = 90 Hours data taking (15 shifts). Lots, but will make a  
 start anyway in case there is opportunity in later data taking for more running. 



 [[analysis:2016-11-19_physics-shifter|Physics post-processing]] 


 h2: Old daily schedules: