RunPlan20161128 » History » Revision 60

« Previous | Revision 60/87 (diff) | Next »
MOM, Mice Operations Manager, 10 December 2016 14:13


RunPlan20161128 to Dec 16th 2016

Scattering data with field, backup plan for straight tracks.

Daily schedule from 28/Nov to 16/Dec.

We expect to be running with 2V beamloss. Note Decay Solenoid is ON. ISIS is at 40+10 and 700 MeV

Note:

Date Dec 4 Dec. 5 Dec. 6 Dec. 7 Dec. 8 Dec. 9 Dec 10
MOM M. Uchida M. Uchida M. Uchida M. Uchida M. Uchida M. Uchida M. Uchida
BLOC R.Gamet R.Gamet R.Gamet R.Gamet J.Greis J.Greis J.Greis
SOC D. Ragaram D. Ragaram D. Ragaram D. Ragaram D. Ragaram D. Ragaram D. Ragaram
Lead shifter (08:00-16:00) R.Gamet R.Gamet R.Gamet R.Gamet S.Wilbur S.Wilbur S.Wilbur
Shifter 2 (08:00-16:00) D.Bowring D.Bowring D.Bowring D.Bowring J.Greis J.Greis J.Greis
Lead shifter (16:00-00:00) P.Soler P.Soler P.Soler P.Soler D.Neuffer D.Neuffer D.Neuffer
Shifter 2 (16:00-00:00) D.Maletic D.Maletic D.Maletic D.Maletic D.Maletic D.Maletic D.Maletic
Lead Shifter (00:00-08:00) M.Courthold M.Courthold P.Kyberd P.Kyberd A.Bross A.Bross A.Bross
Shifter (00:00-08:00) B.Freemire B.Freemire P.Hanlet P.Hanlet B.Freemire B.Freemire B.Freemire
Additional Personnel
Notes
Date Dec 11 Dec. 12 Dec. 13 Dec. 14 Dec. 15 Dec. 16
MOM M. Uchida M. Uchida M. Uchida M. Uchida M. Uchida M. Uchida
BLOC J.Greis J.Greis Y.Song Y.Song Y.Song Y.Song
SOC D. Ragaram D. Ragaram D. Ragaram D. Ragaram D. Ragaram D. Ragaram
Lead shifter (08:00-16:00) S.Wilbur S.Wilbur S.Boyd S.Boyd S.Boyd
Shifter 2 (08:00-16:00) J.Greis J.Greis B.Freemire B.Freemire B.Freemire
Lead shifter (16:00-00:00) D.Neuffer D.Neuffer M.Bonesini M.Bonesini M.Bonesini
Shifter 2 (16:00-00:00) B.Freemire B.Freemire L.Tortora L.Tortora L.Tortora
Lead Shifter (00:00-08:00) A.Bross A.Bross D.Neuffer D.Neuffer D.Neuffer
Shifter (00:00-08:00) D.Maletic D.Maletic Y.Song Y.Song Y.Song
Additional Personnel
Notes

Plan from 9 Dec:

Take H9a and H9c data in two hour chunks until complete. Then cycle through two hours of each H10a-c data until complete.
If this is all done at an unsociable hour. Cycle through two hours H9a-c (in perpetuity) and H10a-c (until 650 triggers each) and repeat.

Data to take

Field On Data

Task H9 - Emittance Reduction!!

Task Momentum # Triggers Beamline Tag CoolingChannel Tag Similar runs Final Event Tally (k)
H9d 200 2e6 TOF1 Diff Mask 8 200+M3-Test1 2016-04-1.7 H4c H7c

| RUN Settings | Diffuser | Proton Absorber | Q1 | Q2 | Q3 | D1 | DS | D2 | Q4 | Q5 | Q6 | Q7 | Q8 | Q9 | | | | mm | A | A | A | A | A | A | A | A | A | A | A | A | | H9d | Mask 8 (Iris 4 closed 1-3 open) | 29 | | | | | ----| | | | | | | |
h4. Task H10 - Magnet alignment

No beamline tags exist. All H10 runs will be made with the magnets manually set to match the beamline tag but with the iris 4 closed and in the comment write eg. "Diff Mask 8 -140+M3_Test2 settings"

Task Momentum # Triggers Beamline Tag CoolingChannel Tag Similar runs
H10a 140 7e5 TOF1 Diff Mask 8 as 3-140+M3_Test2 2016-04-1.7
H10b 170 7e5 TOF1 Diff Mask 8 as 3-170+M3-Test1 2016-04-1.7
H10c 240 7e5 TOF1 Diff Mask 8 as 3-240+M3_Test1 2016-04-1.7

Straight track data (fallback)

Task S2: LiH scattering data.

Task Momentum # Triggers Beamline Tag CoolingChannel Tag Similar runs
S2a 140 1M @ TOF2 3-140+M3-Test2
S2b 200 ? 6-200+M0

Task S2a - 10M triggers at TOF1, 33 triggers/spill = 90 Hours data taking (15 shifts). Lots, but will make a
start anyway in case there is opportunity in later data taking for more running.

Physics post-processing

Step4_Pionic_beam_Tags

Finished data sets:

h4. Task H4 - Emittance Reduction!!

Task Momentum # Triggers Beamline Tag CoolingChannel Tag Similar runs Final event tally
H4a 140 1e6 TOF1 3-140+M3-Test2 2016-04-01.2 1749
H4b 140 1e6 TOF1 6-140+M3-Test2 2016-04-01.2 1694
H4c 140 2e6 TOF1 10-140+M3-Test3 2016-04-01.2 2909

h4. Task H5 - Magnet alignment (DONE)

Task Momentum # Triggers Beamline Tag CoolingChannel Tag Similar runs Final Event tally
H5a 170 5e5 TOF1 3-170+M3-Test1 2016-04-01.2 9.55e6
H5b 200 5e5 TOF1 3-200+M3_Test1 2016-04-01.2 8.92e6
H5c 240 5e5 TOF1 3-240+M3_Test1 2016-04-01.2 7.93e6

h4. Task H6 - Diffuser Scan

The beamline and cooling channel settings remain the same and the diffuser mus be changed manually from the diffuser GUI for each new setting! Be sure to do this AFTER entering the beamline optics, or it will reset the diffuser. (Please note there is no run H6d.

Task Momentum # Triggers Beamline Tag CoolingChannel Tag Diffuser Setting Closed Iris Similar runs Final Event Tally
H6a 170 5e5 TOF1 3-170+M3-Test1 2016-04-01.2 1 1 8498 320
H6b 170 5e5 TOF1 3-170+M3-Test1 2016-04-01.2 2 2 8497 300
H6c 170 5e5 TOF1 3-170+M3-Test1 2016-04-01.2 4 3 8495-6 300
H6e 170 5e5 TOF1 3-170+M3-Test1 2016-04-01.2 6 2+3 8499 300
H6f 170 5e5 TOF1 3-170+M3-Test1 2016-04-01.2 7 1+2+3 8502 301
H6g 170 5e5 TOF1 3-170+M3-Test1 2016-04-01.2 8 4 8494 300
H6h 170 5e5 TOF1 3-170+M3-Test1 2016-04-01.2 9 1+4 8500 300
H6i 170 5e5 TOF1 3-170+M3-Test1 2016-04-01.2 12 3+4 8501 300
H6j 170 5e5 TOF1 3-170+M3-Test1 2016-04-01.2 15 1+2+3+4 8503 300

h4. Task H7 - Emittance Reduction!!(DONE)

Task Momentum # Triggers Beamline Tag CoolingChannel Tag Similar runs final event tally
H7a 140 1e6 TOF1 3-140+M3-Test2 2016-04-1.5 H4a 1494k
H7b 140 1e6 TOF1 6-140+M3-Test2 2016-04-1.5 H4b 1432k
H7c 140 2e6 TOF1 10-140+M3-Test3 2016-04-1.5 H4c 2741k

h4. Task H8 - Magnet alignment (DONE)

Task Momentum # Triggers Beamline Tag CoolingChannel Tag Similar runs final event tally
H8a 170 5e5 TOF1 3-170+M3-Test1 2016-04-1.5 H5a 668k
H8b 200 5e5 TOF1 3-200+M3_Test1 2016-04-1.5 H5b 667k
H8c 240 5e5 TOF1 3-240+M3_Test1 2016-04-1.5 H5c 665

h4. Task H9 - Emittance Reduction!! (DONE)

Task Momentum # Triggers Beamline Tag CoolingChannel Tag Similar runs Final Event Tally (k)
H9a 200 1e6 TOF1 3-200+M3_Test1 2016-04-1.7 H4a H7a 1208
H9b 200 1e6 TOF1 6-200+M3-Test1 2016-04-1.7 H4b H7b 1000
H9c 200 2e6 TOF1 10-200+M3-Test1 2016-04-1.7 H4c H7c 3817

Previous Shifts

Date Nov 28 Nov. 29 Nov. 30 Dec. 1 Dec. 2 Dec. 3
MOM E. Overton M. Uchida M. Uchida M. Uchida M. Uchida M. Uchida
BLOC Y.Song Y.Song Y.Song Y.Song Y.Song R.Gamet
SOC D. Ragaram D. Ragaram D. Ragaram D. Ragaram D. Ragaram D. Ragaram
shifter 2 (08:00-16:00) Y.Song Y.Song Y.Song Y.Song Y.Song D.Bowring
Lead Shifter(08:00-16:00) P. Franchini P. Franchini P. Franchini P. Franchini P. Franchini P.Soler
Lead shifter (16:00-00:00) D. Ragaram D. Ragaram D. Ragaram D. Ragaram D. Ragaram R.Gamet
Shifter 2 (16:00-00:00) B.Freemire B.Freemire B.Freemire B.Freemire B.Freemire D.Maletic
Lead Shifter (00:00-08:00) G. Vankova G. Vankova G. Vankova G. Vankova G. Vankova B.Freemire 4-8
Shifter (00:00-08:00) J. Langlands J. Langlands J. Langlands J. Langlands J. Langlands P.Hanlet 12-4
Additional Personnel M.Courthold
Notes

Updated by MOM, Mice Operations Manager over 6 years ago · 60 revisions