RunPlan20161128 to Dec 16th 2016¶
Scattering data with field, backup plan for straight tracks.
Daily schedule from 28/Nov to 16/Dec.¶
We expect to be running with 2V beamloss. Note Decay Solenoid is ON. ISIS is at 40+10 and 700 MeV
Note:
Date | Nov 28 | Nov. 29 | Nov. 30 | Dec. 1 | Dec. 2 | Dec. 3 |
MOM | E. Overton | M. Uchida | M. Uchida | M. Uchida | M. Uchida | M. Uchida |
BLOC | Y.Song | Y.Song | Y.Song | Y.Song | Y.Song | R.Gamet |
SOC | D. Ragaram | D. Ragaram | D. Ragaram | D. Ragaram | D. Ragaram | D. Ragaram |
shifter 2 (08:00-16:00) | Y.Song | Y.Song | Y.Song | Y.Song | Y.Song | D.Bowring |
Lead Shifter(08:00-16:00) | P. Franchini | P. Franchini | P. Franchini | P. Franchini | P. Franchini | P.Soler |
Lead shifter (16:00-00:00) | D. Ragaram | D. Ragaram | D. Ragaram | D. Ragaram | D. Ragaram | R.Gamet |
Shifter 2 (16:00-00:00) | B.Freemire | B.Freemire | B.Freemire | B.Freemire | B.Freemire | D.Maletic |
Lead Shifter (00:00-08:00) | G. Vankova | G. Vankova | G. Vankova | G. Vankova | G. Vankova | B.Freemire 4-8 |
Shifter (00:00-08:00) | J. Langlands | J. Langlands | J. Langlands | J. Langlands | J. Langlands | P.Hanlet 12-4 |
Additional Personnel | M.Courthold | |||||
Notes |
Date | Dec 4 | Dec. 5 | Dec. 6 | Dec. 7 | Dec. 8 | Dec. 9 |
MOM | M. Uchida | M. Uchida | M. Uchida | M. Uchida | M. Uchida | M. Uchida |
BLOC | R.Gamet | R.Gamet | R.Gamet | R.Gamet | J.Greis | J.Greis |
SOC | D. Ragaram | D. Ragaram | D. Ragaram | D. Ragaram | D. Ragaram | D. Ragaram |
Lead shifter (08:00-16:00) | R.Gamet | R.Gamet | R.Gamet | R.Gamet | S.Wilbur | S.Wilbur |
Shifter 2 (08:00-16:00) | D.Bowring | D.Bowring | D.Bowring | D.Bowring | J.Greis | J.Greis |
Lead shifter (16:00-00:00) | P.Soler | P.Soler | P.Soler | P.Soler | D.Neuffer | D.Neuffer |
Shifter 2 (16:00-00:00) | D.Maletic | D.Maletic | D.Maletic | D.Maletic | D.Maletic | D.Maletic |
Lead Shifter (00:00-08:00) | M.Courthold | M.Courthold | P.Kyberd | P.Kyberd | A.Bross | A.Bross |
Shifter (00:00-08:00) | B.Freemrire | B.Freemrire | P.Hanlet | P.Hanlet | B.Freemrire | B.Freemrire |
Additional Personnel | ||||||
Notes | ||||||
Plan for 2/Dec-5/Dec:¶
Dec 2-4: Data taking: Do 2 hours of each, H4 task task until complete. Then 2 hours each H4 and H5 task (until 7e5) until Monday morning.
Dec 5th: 10am Cooling channel magnet setting changes. Then Begin 2 hrs of each H6 and H7 until complete at new settings.
Data to take¶
Field On Data¶
Do 2 hours of each H4 task, then each H5 task until complete.
Task H4 - Emittance Reduction!!¶
Task | Momentum | # Triggers | Beamline Tag | CoolingChannel Tag | Similar runs |
H4a | 140 | 1e6 TOF1 | 3-140+M3-Test2 | 2016-04-01.2 | |
H4b | 140 | 1e6 TOF1 | 6-140+M3-Test2 | 2016-04-01.2 | |
H4c | 140 | 2e6 TOF1 | 10-140+M3-Test3 | 2016-04-01.2 |
Task H5 - Magnet alignment¶
Task | Momentum | # Triggers | Beamline Tag | CoolingChannel Tag | Similar runs |
H5a | 170 | 5e5 TOF1 | 3-170+M3-Test1 | 2016-04-01.2 | |
H5b | 200 | 5e5 TOF1 | 3-200+M3_Test1 | 2016-04-01.2 | |
H5c | 240 | 5e5 TOF1 | 3-240+M3_Test1 | 2016-04-01.2 |
Task H6 - Diffuser Scan DO NOT TAKE UNLESS INSTRUCTED BY THE MOM.¶
The beamline and cooling channel settings remain the same and the diffuser mus be changed manually for each new setting!
Task | Momentum | # Triggers | Beamline Tag | CoolingChannel Tag | Diffuser Setting | Closed Iris | Similar runs |
H6a | 240 | 5e5 TOF1 | 3-240+M3-Test1 | 2016-04-01.2 | 1 | 1 | 8498 |
H6b | 240 | 5e5 TOF1 | 3-240+M3-Test1 | 2016-04-01.2 | 2 | 2 | 8497 |
H6d | 240 | 5e5 TOF1 | 3-240+M3-Test1 | 2016-04-01.2 | 4 | 3 | 8495-6 |
H6e | 240 | 5e5 TOF1 | 3-240+M3-Test1 | 2016-04-01.2 | 6 | 2+3 | 8499 |
H6f | 240 | 5e5 TOF1 | 3-240+M3-Test1 | 2016-04-01.2 | 7 | 1+2+3 | 8502 |
H6g | 240 | 5e5 TOF1 | 3-240+M3-Test1 | 2016-04-01.2 | 8 | 4 | 8494 |
H6h | 240 | 5e5 TOF1 | 3-240+M3-Test1 | 2016-04-01.2 | 9 | 1+4 | 8500 |
H6i | 240 | 5e5 TOF1 | 3-240+M3-Test1 | 2016-04-01.2 | 12 | 3+4 | 8501 |
H6j | 240 | 5e5 TOF1 | 3-240+M3-Test1 | 2016-04-01.2 | 15 | 1+2+3+4 | 8503 |
Task H7 - Emittance Reduction!!¶
Task | Momentum | # Triggers | Beamline Tag | CoolingChannel Tag | Similar runs |
H7a | 140 | 1e6 TOF1 | 3-140+M3-Test2 | 2016-04-1.5 | H4a |
H7b | 140 | 1e6 TOF1 | 6-140+M3-Test2 | 2016-04-1.5 | H4b |
H7c | 140 | 2e6 TOF1 | 10-140+M3-Test3 | 2016-04-1.5 | H4c |
Task H8 - Magnet alignment¶
Task | Momentum | # Triggers | Beamline Tag | CoolingChannel Tag | Similar runs |
H8a | 170 | 5e5 TOF1 | 3-170+M3-Test1 | 2016-04-1.5 | H5a |
H8b | 200 | 5e5 TOF1 | 3-200+M3_Test1 | 2016-04-1.5 | H5b |
H8c | 240 | 5e5 TOF1 | 3-240+M3_Test1 | 2016-04-1.5 | H5c |
Straight track data (fallback)¶
Task S2: LiH scattering data.¶
Task | Momentum | # Triggers | Beamline Tag | CoolingChannel Tag | Similar runs |
S2a | 140 | 1M @ TOF2 | 3-140+M3-Test2 | ||
S2b | 200 | ? | 6-200+M0 |
Task S2a - 10M triggers at TOF1, 33 triggers/spill = 90 Hours data taking (15 shifts). Lots, but will make a
start anyway in case there is opportunity in later data taking for more running.
h2: Old daily schedules: