RunPlan20161128 to Dec 16th 2016¶
Scattering data with field, backup plan for straight tracks.
Daily schedule from 28/Nov to 16/Dec.¶
We expect to be running with 2V beamloss. Note Decay Solenoid is ON. ISIS is at 40+10 and 700 MeV
Note:
Date | Nov 28 | Nov. 29 | Nov. 30 | Dec. 1 | Dec. 2 | Dec. 3 |
MOM | E. Overton | M. Uchida | M. Uchida | M. Uchida | M. Uchida | M. Uchida |
BLOC | Y.Song | Y.Song | Y.Song | Y.Song | Y.Song | R.Game |
SOC | D. Ragaram | D. Ragaram | D. Ragaram | D. Ragaram | D. Ragaram | D. Ragaram |
shifter 2 (08:00-16:00) | Y.Song | Y.Song | Y.Song | Y.Song | Y.Song | D.Bowring |
Lead Shifter(08:00-16:00) | P. Franchini | P. Franchini | P. Franchini | P. Franchini | P. Franchini | R.Gamet |
Lead shifter (16:00-00:00) | D. Ragaram | D. Ragaram | D. Ragaram | D. Ragaram | D. Ragaram | P.Soler |
Shifter 2 (16:00-00:00) | B.Freemire | B.Freemire | B.Freemire | B.Freemire | B.Freemire | D.Maletic |
Lead Shifter (00:00-08:00) | G. Vankova | G. Vankova | G. Vankova | G. Vankova | G. Vankova | B.Freemire 12-4 |
Shifter (00:00-08:00) | J. Langlands | J. Langlands | J. Langlands | J. Langlands | J. Langlands | P.Hanlet 4-8 |
Additional Personnel | M.Courthold | |||||
Notes |
Date | Dec 4 | Dec. 5 | Dec. 6 | Dec. 7 | Dec. 8 | Dec. 9 |
MOM | M. Uchida | M. Uchida | M. Uchida | M. Uchida | M. Uchida | M. Uchida |
BLOC | R.Game | R.Game | R.Game | R.Game | J.Greis | J.Greis |
SOC | D. Ragaram | D. Ragaram | D. Ragaram | D. Ragaram | D. Ragaram | D. Ragaram |
Lead shifter (08:00-16:00) | R.Gamet | R.Gamet | R.Gamet | R.Gamet | S.Wilbur | S.Wilbur |
Shifter 2 (08:00-16:00) | D.Bowring | D.Bowring | D.Bowring | D.Bowring | J.Greis | J.Greis |
Lead shifter (16:00-00:00) | P.Soler | P.Soler | P.Soler | P.Soler | D.Neuffer | D.Neuffer |
Shifter 2 (16:00-00:00) | D.Maletic | D.Maletic | D.Maletic | D.Maletic | D.Maletic | D.Maletic |
Lead Shifter (00:00-08:00) | M.Courthold | M.Courthold | P.Kyberd | P.Kyberd | A.Bross | A.Bross |
Shifter (00:00-08:00) | B.Freemrire | B.Freemrire | B.Freemrire | B.Freemrire | ||
Additional Personnel | ||||||
Notes | Mag. Mon. overnight | Mag. Mon. overnight | ||||
Plan for 2/Dec-5/Dec:¶
Dec 2nd: Shifter training-> 9-16:30, Data taking 08:00-11:00 and 16:30-00:00.
Dec 2-4: Data taking: Do 2 hours of each, H4 task task until complete. Then 2 hours each H4 and H5 task (until 7e5) until Monday morning.
Dec 5th: 10am Cooling channel magnet setting changes. Then Begin 2 hrs of each H6 and H7 until complete at new settings.
Data to take¶
Field On Data¶
Do 2 hours of each H4 task, then each H5 task until complete.
Task H4 - Emittance Reduction!!¶
Task | Momentum | # Triggers | Beamline Tag | CoolingChannel Tag | Similar runs |
H4a | 140 | 1e6 TOF1 | 3-140+M3-Test2 | 2016-04-01.2 | |
H4b | 140 | 1e6 TOF1 | 6-140+M3-Test2 | 2016-04-01.2 | |
H4c | 140 | 2e6 TOF1 | 10-140+M3-Test3 | 2016-04-01.2 |
Task H5 - Magnet alignment¶
Task | Momentum | # Triggers | Beamline Tag | CoolingChannel Tag | Similar runs |
H5a | 170 | 5e5 TOF1 | 3-170+M3-Test1 | 2016-04-01.2 | |
H5b | 200 | 5e5 TOF1 | 3-200+M3_Test1 | 2016-04-01.2 | |
H5c | 240 | 5e5 TOF1 | 3-240+M3_Test1 | 2016-04-01.2 |
Task H6 - Emittance Reduction!!¶
Task | Momentum | # Triggers | Beamline Tag | CoolingChannel Tag | Similar runs |
H6a | 140 | 1e6 TOF1 | 3-140+M3-Test2 | NA2016-04-01.2 | H4a |
H6b | 140 | 1e6 TOF1 | 6-140+M3-Test2 | NA2016-04-01.2 | H4b |
H6c | 140 | 2e6 TOF1 | 10-140+M3-Test3 | NA2016-04-01.2 | H4c |
Task H7 - Magnet alignment¶
Task | Momentum | # Triggers | Beamline Tag | CoolingChannel Tag | Similar runs |
H7a | 170 | 5e5 TOF1 | 3-170+M3-Test1 | NA2016-04-01.2 | H5a |
H7b | 200 | 5e5 TOF1 | 3-200+M3_Test1 | NA2016-04-01.2 | H5b |
H7c | 240 | 5e5 TOF1 | 3-240+M3_Test1 | NA2016-04-01.2 | H5c |
Straight track data (fallback)¶
Task S2: LiH scattering data.¶
Task | Momentum | # Triggers | Beamline Tag | CoolingChannel Tag | Similar runs |
S2a | 140 | 1M @ TOF2 | 3-140+M3-Test2 | ||
S2b | 200 | ? | 6-200+M0 |
Task S2a - 10M triggers at TOF1, 33 triggers/spill = 90 Hours data taking (15 shifts). Lots, but will make a
start anyway in case there is opportunity in later data taking for more running.
h2: Old daily schedules:
Updated by George, Melissa almost 7 years ago · 14 revisions