RunPlan20161128 » History » Revision 10

Revision 9 (George, Melissa, 01 December 2016 17:42) → Revision 10/87 (George, Melissa, 01 December 2016 17:44)

h1. RunPlan20161128 to Dec 16th 2016 

 Scattering data with field, backup plan for straight tracks. 

 h3. Daily schedule from 28/Nov to 3/Dec. 

 We expect to be running with 2V beamloss. Note Decay Solenoid is ON. ISIS is at 40+10 and 700 MeV 

 Note:  


 | Date                           | Nov 28          |    Nov. 29          |    Nov. 30          |    Dec. 1          |    Dec. 2           |    Dec. 3          |  
 | MOM                            | E. Overton      |    M. Uchida        |    M. Uchida        |    M. Uchida       |     M. Uchida       |    M. Uchida       | 
 | BLOC                           | Y.Song          |    Y.Song           |    Y.Song           |    Y.Song          |     Y.Song          |    R.Game          | 
 | SOC                            | D. Ragaram      |    D. Ragaram       |    D. Ragaram       |    D. Ragaram      |     D. Ragaram      |    D. Ragaram      | 
 | shifter 2 (08:00-16:00)        | Y.Song          |    Y.Song           |    Y.Song           |    Y.Song          |     Y.Song          |    D.Bowring       | 
 | Lead Shifter(08:00-16:00)      | P. Franchini    |    P. Franchini     |    P. Franchini     |    P. Franchini    |     P. Franchini    |    R.Gamet         | 
 | Lead shifter (16:00-00:00)     | D. Ragaram      |    D. Ragaram       |    D. Ragaram       |    D. Ragaram      |     D. Ragaram      |    P.Soler         | 
 | Shifter 2    (16:00-00:00)       | B.Freemire      |    B.Freemire       |    B.Freemire       |    B.Freemire      |     B.Freemire      |    D.Maletic       | 
 | Lead Shifter    (00:00-08:00)    | G. Vankova      | G. Vankova        |    G. Vankova       |    G. Vankova      |     G. Vankova      |B.Freemire 12-4 | 
 | Shifter          (00:00-08:00) | J. Langlands    | J. Langlands      |    J. Langlands     |    J. Langlands    |     J. Langlands    |    P.Hanlet 4-8    | 
 | Additional Personnel           |                 |                   |                   |                  |                   |                  | 
 | Notes                          |                 |                   |                  |                   |                  |Mag. Mon. overnight 
 |                             |    |                |                   |                  |                   |                  | 


 | Date                           | Dec 4           |    Dec. 5           |    Dec. 6           |    Dec. 7          |    Dec. 8           |    Dec. 9         |   
 | MOM                            | M. Uchida       |    M. Uchida        |    M. Uchida        |    M. Uchida       |     M. Uchida       |    M. Uchida      | 
 | BLOC                           | R.Game          |    R.Game           |    R.Game           |    R.Game          |     J.Greis         |    J.Greis        | 
 | SOC                            | D. Ragaram      |    D. Ragaram       |    D. Ragaram       |    D. Ragaram      |     D. Ragaram      |    D. Ragaram     | 
 | Lead shifter (08:00-16:00)     | R.Gamet         |    R.Gamet          |    R.Gamet          |    R.Gamet         |     S.Wilbur        |    S.Wilbur       | 
 | Shifter 2    (08:00-16:00)       | D.Bowring       |    D.Bowring        |    D.Bowring        |    D.Bowring       |     J.Greis         |    J.Greis        | 
 | Lead shifter (16:00-00:00)     | P.Soler         |    P.Soler          |    P.Soler          |    P.Soler         |     D.Neuffer       |    D.Neuffer      | 
 | Shifter 2    (16:00-00:00)       | D.Maletic       |    D.Maletic        |    D.Maletic        |    D.Maletic       |     D.Maletic       |    D.Maletic      | 
 | Lead Shifter    (00:00-08:00)    | M.Courthold     |    M.Courthold      |    P.Kyberd         |    P.Kyberd        |     A.Bross         |    A.Bross        | 
 | Shifter          (00:00-08:00) | B.Freemrire     |    B.Freemrire      |                   |                  |     B.Freemrire     |    B.Freemrire    | 
 | Additional Personnel           |                 |                   |                   |                  |                   |                 | 
 | Notes                          | |                |                   | Mag. Mon. overnight|     Mag. Mon. overnight       |                 | 
 |                             |    |                |                   |                  |                   |                 | 

 h3. Plan for 2/Dec-5/Dec: 

 Dec 2nd: Shifter training-> 9-16:30, Data taking 08:00-11:00 and 16:30-00:00. 
 Dec 2-4: Data taking: Do 2 hours of each, H4 task task until complete. Then 2 hours each H4 and H5 task until Monday morning. 
 Dec 5th: 10am Cooling channel magnet setting changes. Then Begin 2 hrs of each H6 and H7 until complete at new settings. 

 h1. Data to take 

 h2. Field On Data 

 Do 2 hours of each H4 task, then each H5 task until complete. 

 h4. Task H4 - Emittance Reduction!! 

 | *Task*     | *Momentum* | *# Triggers*     | *Beamline Tag*        |    *CoolingChannel Tag*    | *Similar runs*     | 
 | H4a         |     140        |     1e6 TOF1       |        3-140+M3-Test2     |       2016-04-01.2     |                  | 
 | H4b         |     140        |     1e6 TOF1       |        6-140+M3-Test2    |       2016-04-01.2     |                  | 
 | H4c         |     140        |     2e6 TOF1       |        10-140+M3-Test3    |       2016-04-01.2     |                  | 

 h4. Task H5 - Magnet alignment 

 | *Task*     | *Momentum* | *# Triggers*     | *Beamline Tag*        |    *CoolingChannel Tag*    | *Similar runs*     | 
 | H5a         |     170        |     5e5 TOF1       |      3-170+M3-Test1     |       2016-04-01.2     |                  | 
 | H5b         |     200        |     5e5 TOF1      |      3-200+M3_Test1 |       2016-04-01.2     |                  | 
 | H5c         |     240        |     5e5 TOF1       |      3-240+M3_Test1    |       2016-04-01.2     |                  | 

 h4. Task H6 - Emittance Reduction!! 

 | *Task*     | *Momentum* | *# Triggers*     | *Beamline Tag*        |    *CoolingChannel Tag*    | *Similar runs*     | 
 | H6a H4a         |     140        |     1e6 TOF1       |        3-140+M3-Test2     |       NA2016-04-01.2     |      H4a                            | 
 | H6b H4b         |     140        |     1e6 TOF1       |        6-140+M3-Test2    |       NA2016-04-01.2     |       H4b                           | 
 | H6c H4c         |     140        |     2e6 TOF1       |        10-140+M3-Test3    |       NA2016-04-01.2     |      H4c                            | 

 h4. Task H7 - Magnet alignment 

 | *Task*     | *Momentum* | *# Triggers*     | *Beamline Tag*        |    *CoolingChannel Tag*    | *Similar runs*     | 
 | H7a H5a         |     170        |     5e5 TOF1       |      3-170+M3-Test1     |       NA2016-04-01.2     |        H5a                          | 
 | H7b H5b         |     200        |     5e5 TOF1      |      3-200+M3_Test1 |       NA2016-04-01.2     |           H5b                       | 
 | H7c H5c         |     240        |     5e5 TOF1       |      3-240+M3_Test1    |       NA2016-04-01.2     |         H5c                         | 


 h2. Straight track data (fallback) 

 h3. Task S2: LiH scattering data. 

 | *Task*      | *Momentum* | *# Triggers*     | Beamline Tag         | CoolingChannel Tag    | Similar runs     | 
 | S2a         |     140        |    1M     @ TOF2     |    3-140+M3-Test2      |                      |                  | 
 | S2b         |     200        |    ?               |        6-200+M0        |                      |                  | 

 Task S2a - 10M triggers at TOF1, 33 triggers/spill = 90 Hours data taking (15 shifts). Lots, but will make a  
 start anyway in case there is opportunity in later data taking for more running. 



 [[analysis:2016-11-19_physics-shifter|Physics post-processing]] 