Run Plan 22nd - 25th September

Summary of aims and timing of the run.

Daily schedule

22/09 22/09 23/09 23/09 24/09 24/09 25/09 25/09
estimated time 8am - 4pm 4pm - 11:59pm 8am - 4pm 4pm - 11:59pm 8am - 4pm 4pm - 11:59pm 8am - 4pm 4pm - 11:59pm
MOM C.Rogers C. Rogers C.Rogers/P. Franchini P. Franchini P. Franchini P. Franchini P. Franchini P. Franchini
Lead shifter C. Heidt M. Bogomilov M. Bogomilov G. Vankova M. Bogomilov M. Bogomilov M. Bogomilov M. Bogomilov
Shifter 2 M. Savik K. Long J. Martyniak J. Pasternak J. Martyniak J. Pasternak J. Martyniak J. Pasternak
BLOC C. Heidt C.Heidt ? ? ? ? C. Heidt C. Heidt
Beam? Yes Yes Yes Yes Yes Yes Yes Yes
Additional Personnel

Data Requested

  • Shifter training Thursday am
  • TOF calibration
  • Detector alignment
  • Beamline studies

Beamline Configurations

We expect to be running with 2V beamloss and beam bump active. Note Decay Solenoid is OFF.

Reference Run without Decay Solenoid

Particle Species p at Tgt p@D1 p@D2 p@Tof0 Proton Absorber Q1 Q2 Q3 D1 DS D2 Q4 Q5 Q6 Q7 Q8 Q9 Ran? Similar Run(s)
MeV/c MeV/c MeV/c MeV/c mm A A A A A A A A A A A A DAQ run #
pion 272.42 268.67 265.98 143.4 29 57.8 105.6 64.6 202.8 ---- 100.4 176.8 237.1 157.2 157.6 238.5 203.7

Task 1: TOF Calibration

Task Description Momentum # Triggers # shifts SSU (ECE) SSU M1/M2 FC SSD (ECE) SSD M1/M2 RunControl Tag
1 TOF Calibration 300 MeV/c 500k @ TOF1 1 N N/N N N N/N ToF-Calib-NoDS

Task 2: Detector alignment

Task 2a: 200 MeV/c

Task Momentum # Triggers SSU (ECE) SSU M1/M2 FC SSD (ECE) SSD M1/M2 RunControl Tag
2a 200 200k at TOF1 N N/N N N N/N 6-200+M0
Particle Species Pz @ TKU Station 5 Proton Absorber Diffuser setting Q1 Q2 Q3 D1 DS D2 Q4 Q5 Q6 Q7 Q8 Q9 RunControl Tag
MeV/c mm A A A A A A A A A A A A
muons/pions 200 29 no diffuser 51.63 94.37 57.74 180.7 94.91 159.44 213.82 141.76 69.99 105.93 90.44 3-200+M3-NoDS-Test1

Task 2b: 300 MeV/c

Number of pulses Beamloss Particle Species p at Tgt p@D1 p@D2 Proton Absorber Q1 Q2 Q3 D1 DS D2 Q4 Q5 Q6 Q7 Q8 Q9 Similar Run(s) Run Tag
# V mm A A A A A A A A A A A A A A A A DAQ run #
1000k TOF1 1 Pion 300.0 82 72.7 133.0 81.4 261.1 ---- 131.5 244.3 300.6 199.4 204.7 309.9 264.9 -- Alignment_300_noDS-test1

Task 2c: 400 MeV/c (Final setting after the D2/quads tuning)

Number of pulses Beamloss Particle Species p at Tgt p@D1 p@D2 Proton Absorber Q1 Q2 Q3 D1 DS D2 Q4 Q5 Q6 Q7 Q8 Q9 Similar Run(s) Run Tag
# V mm A A A A A A A A A A A A A A A A DAQ run #
200k TOF1 1 Pion 400.0 82 96.55 176.6 108.1 370.1 ---- 170 213.1 285.7 189.5 193.7 293.3 250.6 -- Alignment_400_noDS-test1

Task 3: Beamline optimisation

By Paolo's command

Updated by Franchini, Paolo almost 7 years ago ยท 27 revisions