MOM, Mice Operations Manager, 14 March 2016 11:37


Daily Run Plan 15th and 16th March 2016

Daily schedule

Days 15-16 Mar
estimated time 08:00 - 16:00 16:00 - 00:00
MOM R. Bayes R. Bayes
Lead shifter D. Saunders C. Hunt
Shifter 2 L. Cremaldi S. Ricciardi
BLOC A. Dobbs A. Dobbs
SOC J. Nugent J. Nugent
Experimenter J. Nugent J. Nugent
Aim LiH absorber data LiH absorber data
Beam? Yes Yes

Shift plan:

  • 07:30 : MOM and BLOC start-up
  • 08:00 : start of shift 1
  • ??:00 on the 15th: DAQ test
  • 15:55 : end of shift 1
  • 16:30 : start of shift 2
  • 23:30 : Stop data-taking, full shutdown of target, unlock and open hall
  • 00:00 : end of shift

Beamline Configurations

We expect to be running with 1-2 beamloss and beam bump active.
DS to be available after morning ramp on Saturday 12th March

Data Requested

  • Tracker calibration (standard procedure)
  • Pion reference run
  • DAQ stress test
  • Muon beam scattering in LiH

Task 0: Tracker calibration (start of each shift) and pion reference run (start of each day)

Task 1: DAQ stress test.

  • Requested 1 hour with a TOF1 rate greater than 200 counts/spill.
  • Should be reasonable with reference beam with DS.
  • Ensure that Yordan knows when these data are to be taken.

Task 2: Muon Beam Scattering Studies:

Will repeat zero absorber studies with LiH

Task 2a : LiH absorber data : 600k TOF2 triggers : (3, 200) Muon Beam with DS

Particle Species p at Tgt p@D1 p@D2 p@Tof0 Proton Absorber Q1 Q2 Q3 D1 DS D2 Q4 Q5 Q6 Q7 Q8 Q9 TOF2 Triggers Tag
MeV/c MeV/c MeV/c MeV/c mm A A A A A A A A A A A A
muon 83 97.7 122.0 84.9 305.0 637.9 91.5 153.4 205.7 136.4 133.9 202.5 172.9 600k 3-200+M0

Task 2b : LiH absorber data : 600k TOF2 triggers : (3, 240) Muon Beam with DS

Particle Species p at Tgt p@D1 p@D2 p@Tof0 Proton Absorber Q1 Q2 Q3 D1 DS D2 Q4 Q5 Q6 Q7 Q8 Q9 TOF2 Triggers Tag
MeV/c MeV/c MeV/c MeV/c mm A A A A A A A A A A A A
muon -- -- -- -- 147 113.7 142.1 98.9 370.5 743 104.4 176.2 236.3 156.7 157.0 237.6 203.0 600k 3-240+M0

Task 2c : LiH absorber data : 600k TOF2 triggers : (3, 172) Muon Beam with DS (settings from this spreadsheet)

Particle Species p at Tgt pSol pDiff p@Tof0 Proton Absorber Q1 Q2 Q3 D1 DS D2 Q4 Q5 Q6 Q7 Q8 Q9 TOF2 Triggers Tag
MeV/c MeV/c MeV/c MeV/c mm A A A A A A A A A A A A
pion/muon 390 221 179.4 78 97.69 122.04 84.91 304.97 637.88 87.69 146.70 196.73 130.40 126.96 192.07 163.96 600k 3-172+M0