Daily run plan : Mar 11, 2016

Daily schedule

Day 11 Mar
estimated time 8:00 - 16:00 16:00 - 00:00
MOM Ryan Bayes
Lead shifter
Shifter 2
BLOC Jan Greis Jan Greis
SOC Jan Greis Jan Greis
Experimenter Jan Greis & Paolo Franchini
Aim Beam rate study
Beam? Yes

Shift plan:

Task 0: Reference Run
Task 1: LiH Scattering with DS off

Beamline Configurations

DS - off due to slow cooling.

Data Requested

Will not conduct rate studies as they are no longer valid. Will instead conduct field off scattering studies with pion beam.

  • Pion reference run (standard procedure)
  • LiH absorber studies.

Task 0: Pion reference run

Task1: (3,240) Pion Beam

Particle Species p at Tgt p@D1 p@D2 p@Tof0 Proton Absorber Q1 Q2 Q3 D1 DS D2 Q4 Q5 Q6 Q7 Q8 Q9 TOF2 Triggers
MeV/c MeV/c MeV/c MeV/c mm A A A A A A A A A A A A
pion 292 288.37 285.77 283.07 147 61.98 113.31 69.35 218.49 ---- 107.6 190.11 254.95 169.08 171.22 259.13 221.37 600k

Phone details for 4pm daily run meeting

Phone access : ReadyTalk number

US 866-740-1260

UK 0800-496-0576

Swiss 0800-70-53-51

Italy 800182592

Access Code: 2155402

Updated by Franchini, Paolo over 7 years ago ยท 8 revisions