Daily Run plan : Feb 25-27, 2016¶
Daily schedule¶
Days | 25-27 Feb | |
estimated time | 9:00 - 17:00 | 17:00 - 00:00 |
MOM | P. Kyberd | |
Lead shifter | R. Gamet | D. Orestano |
Shifter 2 | G. Vankova | M. Bonesini |
BLOC | H. Nebrensky | |
SOC | C. Rogers | |
Experimenter | MOM | |
Aim | Alignment data | |
Beam? | Yes |
Shift plan:¶
- 9am: start of shift
- 16:00pm : Daily run meeting
- 10pm : end of shfit
- Put target in standby
- Hall kept locked
Beamline Configurations¶
We expect to be running with 1-2 beamloss and beam bump active.
No DS.
Data Requested¶
- Tracker calibration (standard procedure)
- Pion reference run
- TOF Calibration
Task 0: Tracker calibration (start of each shift) and pion reference run (start of each day)¶
Task 1: Zero absorber data : 600k TOF2 triggers : 3pi-240-M0 muon beam without DS¶
Particle Species | p at Tgt | p@D1 | p@D2 | p@Tof0 | Proton Absorber | Q1 | Q2 | Q3 | D1 | DS | D2 | Q4 | Q5 | Q6 | Q7 | Q8 | Q9 | TOF2 Triggers |
MeV/c | MeV/c | MeV/c | MeV/c | mm | A | A | A | A | A | A | A | A | A | A | A | A | ||
pion | 292 | 288.37 | 285.77 | 283.07 | 147 | 61.98 | 113.31 | 69.35 | 218.49 | ---- | 107.6 | 190.11 | 254.95 | 169.08 | 171.22 | 259.13 | 221.37 | 600k |
Task 2 : Zero absorber data : 600k TOF2 triggers : (3,172) Pion Beam¶
Particle Species | p at Tgt | p@D1 | p@D2 | p@Tof0 | Proton Absorber | Q1 | Q2 | Q3 | D1 | DS | D2 | Q4 | Q5 | Q6 | Q7 | Q8 | Q9 | TOF2 Triggers |
MeV/c | MeV/c | MeV/c | MeV/c | mm | A | A | A | A | A | A | A | A | A | A | A | A | ||
pion | 232.5 | 228.41 | 225.44 | 222.37 | 78 | 49.14 | 89.82 | 54.95 | 171.69 | ---- | 85.71 | 149.6 | 200.62 | 132.94 | 129.11 | 195.26 | 166.61 | 600k |
Phone details for 4pm daily run meeting¶
Phone access : ReadyTalk number
US 866-740-1260
UK 0800-496-0576
Swiss 0800-70-53-51
Italy 800182592
Access Code: 2155402
Updated by Boyd, Steven over 7 years ago ยท 6 revisions