Mock data run 2: 5th March January 2015

Goal

Ensure readiness for 8th March run.

Start time : 9 am
End time : TBD

Systems

System Expert Arrival Departure Docs Status
Beamline
PPS Craig MacWaters Local
Target Henry Nebrensky Local
Decay Sol Chris White/Henry Local
NC Magnets Henry Nebrensky Local
Beamstop Henry Nebrensky Local
Proton Abs (Henry Nebrensky) Local
Diffuser Pierrick Hanlet Local
Detectors
TOF
Ckov Pierrick Hanlet Local
LM
DAQ
Tracker DAQ N/A
PID DAQ Yordan Karadzhov 3/5/2015
Old Trigger Yordan Karadzhov 3/5/2015
New Trigger Yordan Karadzhov 3/5/2015
Computing
Controls Pierrick Hanlet Local
MLCR Servers Paolo Francini Local
Datamover Janusz Martyniak
Online Recon Adam Dobbs
Online Monitoring Rhys Gardener Local

Prerequisites

20150225_RunPreparationList

Preparations

Representatives from each sub-detector must be available and present at
RAL to ensure that their systems are running properly during the week before this test.
During this week will do individual tests of each of the systems. A preliminary plan is:

3rd March Ensure that the trigger is ready, the control room systems are up and running and the controls are ready
4th March Test TOF
4th March Full system test

Run Plan

Name Target Frame Proton Absorber Beam Stop Diffuser Q1 Q2 Q3 D1 DS D2 Q4 Q5 Q6 Q7 Q8 Q9 Trigger Time
bitmask bitmask A A A A A A A A A A A A mins
Test 1 Raised 0000 Closed 0000 102.4 127.9 89 323.2 669 94.2 158.1 212 140.6 138.7 209.8 179.2 New, TOF1 30
Test 2 Lowered 1111 Closed 1111 184.4 101.2 112.6 0 200.0 0 295.0 395.6 260.9 197.8 298.4 253.52 New, TOF1 30
Test 3 Lowered 0000 Closed 0000 102.4 127.9 89 323.2 669 94.2 158.1 212 140.6 138.7 209.8 179.2 New, TOF0 10
Test 4 Lowered 0000 Closed 0000 102.4 127.9 89 323.2 669 94.2 158.1 212 140.6 138.7 209.8 179.2 New, TOF1 10
Test 5 Lowered 0000 Closed 0000 102.4 127.9 89 323.2 669 94.2 158.1 212 140.6 138.7 209.8 179.2 Old, TOF0 30
Test 6 Lowered 0000 Closed 0000 102.4 127.9 89 323.2 669 94.2 158.1 212 140.6 138.7 209.8 179.2 Old, TOF1 10
Test 7 Lowered 0000 Closed 0000 102.4 127.9 89 323.2 669 94.2 158.1 212 140.6 138.7 209.8 179.2 RC Reference 20
Test 8 Lowered 0000 Closed 0000 102.4 127.9 89 323.2 669 94.2 158.1 212 140.6 138.7 209.8 179.2 RC Test 30
  • Aim of rotating the trigger is to check readout of each TOF detector with old and new trigger. Should be possible to at least check up to e.g. slab hits or uncalibrated space points this way.
    • Sounds like TOF2 cannot be dealt with in this way.
  • Check CKOV
  • Note this will not check some of ToF2, KL, EMR, or Tracker systems.

Beamline tests

  • Check to see if C&M is updating CDB okay
  • Test RunControl Reference Run
  • Test RunControl TEST Run

Detector and DAQ tests

  • Power all detectors
  • Power DAQ with new trigger, then old trigger (new trigger is priority now)
  • Run online monitoring
  • Run online reconstruction
  • Check that online monitoring observes signals from Tof0/Tof1/CKOV
  • Check that online reconstruction reconstructs data correctly
  • Check that data mover moves data to GRID and offline reconstruction goes