RunPlan20151001¶
October | 3-7 | ||
estimated time | 08:00 - 16:00 | 16:00 - 00:00 | 00:00 - 08:00 |
MOM | Y. Karadzhov | Y. Karadzhov | Y. Karadzhov |
Lead Shifter | Alex | Alan | Jaroslaw |
Shifter 1 | Tanaz | Ao | Durga |
BLOC | Celeste (weekend) | ||
SOC | Chris H | ||
Experimenter | |||
Aim | Data taking | Data taking | Data taking |
Beam? | Yes | Yes | |
Additional Personnel | |||
Configuration¶
- SSU at design current
- the DS PSU will be run in local mode, and at fixed current, until a ramp-circuit fault has been identified & fixed.
It is imperative that the DS PSU is operated only by designated DS experts with appropriate
experience - ie Mark Tucker, Vicky Bayliss, and myself. The current is currently set to ????
Known Issues¶
New Shift Checklist¶
The shift checklist can be found in the eLog.
Please go through the checklist at least every two hours.
Hall probe monitoring and operation¶
Melissa would like shifters to take data with the hall probes once per shift. The operating instructions can be found here