RunPlan20150722¶
September | 21 | ||
estimated time | 14:30 - 17:00 | 17:00-20:00 | 20:00 - 06:00 |
MOM | Y. Karadzhov | Y. Karadzhov | Y. Karadzhov |
Lead Shifter | Ao | Ao | Ao / Durga |
Shifter 1 | David | David | Maryian |
BLOC | C. Heidt / Pierrick | C. Heidt / Pierrick | C. Heidt / Pierrick |
SOC | C. Rogers | C. Rogers | C. Rogers |
Experimenter | |||
Aim | Set up for data-taking | Data-taking Validation | Data taking |
Beam? | Yes(?) | Yes(?) | Yes(?) |
Additional Personnel | |||
Beamline Configurations¶
We expect to be running with 2V beamloss and beam bump active.
System configuration¶
- We will not run with the decay solenoid.
- We will use Pierrick's new Run Control at the beginning, if possible. If not we revert to the previous one and kill run control between every run.
- Runs will be 2 hours long.
- We need an (or two) expert supervisor(s) for the 17:00 - 00:00 period.
- We need a Deputy MOM to shut down in the morning, unless Yordan thinks he can be at the MCR before 8am.
Data plan¶
Assuming beam starts at 19:00 and ends at 08:00 (17 hours)
- 140 MeV Pion run with SSU coils around 100 A
Updated by Boyd, Steven about 8 years ago ยท 7 revisions