RunPlan20150722

September 21
estimated time 14:30 - 17:00 17:00-20:00 20:00 - 06:00
MOM Y. Karadzhov Y. Karadzhov Y. Karadzhov
Lead Shifter Ao Ao Ao / Durga
Shifter 1 David David Maryian
BLOC C. Heidt / Pierrick C. Heidt / Pierrick C. Heidt / Pierrick
SOC C. Rogers C. Rogers C. Rogers
Experimenter
Aim Set up for data-taking Data-taking Validation Data taking
Beam? Yes(?) Yes(?) Yes(?)
Additional Personnel

Beamline Configurations

We expect to be running with 2V beamloss and beam bump active.

System configuration

  • We will not run with the decay solenoid.
  • We will use Pierrick's new Run Control at the beginning, if possible. If not we revert to the previous one and kill run control between every run.
  • Runs will be 2 hours long.
  • We need an (or two) expert supervisor(s) for the 17:00 - 00:00 period.
  • We need a Deputy MOM to shut down in the morning, unless Yordan thinks he can be at the MCR before 8am.

Data plan

Assuming beam starts at 19:00 and ends at 08:00 (17 hours)

  1. 140 MeV Pion run with SSU coils around 100 A

Updated by Boyd, Steven about 8 years ago ยท 7 revisions