Preparation for running and training shifters

Daily schedule

July 15
estimated time 9:30-11:00 11:00-12:00 14:00-16:00 16:00-20:00
MOM R. Bayes R. Bayes R. Bayes R. Bayes
Lead shifter P. Hanlet H. Nebrensky C. Pidcott R. Bayes
Shifter 2 C. Rogers Trainees Trainees
BLOC Joe Joe Joe Joe
SOC
Experimenter
Aim Expert Setup Bump Tuning Control Room Training Shadow shift
Beam? No? Yes Yes? Yes?
Additional Personnel D. Adams

Beamline Configurations

We expect to be running with 2V beamloss and beam bump active. Beam line training will be conducted.

Shift plan

  • Expert shift to be focussed on preparations for the bump tuning
    • Hall is currently open
    • If there is work in the hall, that takes priority prior to the bump tuning
  • Bump tuning to be done in cooperation with ISIS
    • may not be moved
    • takes priority over other work
  • Control room training
    • may need to be done with no access to the beam/target
  • Shadow shift
    • depends on the whims of the tracker group.

Data Requested

TOF calibration data

Run Time Preparedness.

  • Downstream PID Detectors (EMR/KL/TOF)
    • in final positions
    • HV on
  • Upstream PID Detectors (Ckov/TOFs)
    • in final positions -- Done (July 4)
  • Trackers
    • Helium on
      • downstream tracker -- Done (July 3)
      • Upstream tracker still has a leak
    • Repair dead channels.
  • Run Control
    • CDB interface
      • Need to improve stability of run control - remove need for IOC restart
    • CDB beam line control
      • Starting beam line current from zero doesn't work due to polarimeter -- Fixed (July 12)
  • Beam line control
    • "Set all to 0" button has not operated in a predictable manner -- Corrected. (July 12)
  • Beam line
    • Decay Solenoid is not on standby -- Quenched July 14
    • Correcting limits on the alarm handler.

Expected Work in the Hall

  • Work on ODH system
  • Pipe welding
    • should have taken two days.
    • does not appear to have started.

Phone details for 6pm daily meeting

Phone access : ReadyTalk number

US 866-740-1260

UK 0800-496-0576

Swiss 0800-70-53-51

Italy 800182592

Access Code: 2155402

Updated by Bayes, Ryan about 8 years ago ยท 4 revisions