Run Planning Discussion 3 July, 2015¶
Magnet training. Will take beam with pion beams to fill out remainder of alignment requirements.
Daily schedule¶
July | 3 |
estimated time | 10pm - 6am |
MOM | R. Bayes |
Lead shifter | Mariyan Bogomilov |
Shifter 2 | Dan Kaplan |
BLOC | A. Dobbs |
SOC | C. Pidcott |
Experimenter | |
Physics Shifter | F. Drielsma |
Aim | Magnet commissioning |
Beam? | No |
Additional Personnel |
Hall Status¶
- The priority is placed on the magnet preparation activities.
- Cooling SSD and SSD is "complete".
- TOF1 will be moved out of the beam line for required Tracker repairs Friday morning. The leak was found too late to put TOF1 in. Data taken using a TOF0 trigger would be of questionable value. Thus we will not take data tonight.
Shift plan:¶
- 10pm
Shifters arrive at hall prepared to monitor the solenoid cold mass pressures anticipating further instability in the instrumentation.
Data Requested¶
- The total estimated data requirement for the tracker to tracker alignment was 300000 tracks.
- The total number of TOF2 events collected since 20 June (when the tracker was stabilized so that useful data could be collected) is 877156. This number is based on the count from the CDB including both muon and pion runs. This number omits runs with no end of run transmission (including run 7168 which was composed of 70k TOF2 triggers generated from a muon beam).
- This suggests that any beam we take tonight will not provide a significant increase in the generated statistics.
Beamline Configuration¶
- No beams will be generated tonight.
Notes for shifters¶
- Please continue to log information into the e-log independent of run information.
Phone details for 6pm daily meeting¶
Phone access : ReadyTalk number
US 866-740-1260
UK 0800-496-0576
Swiss 0800-70-53-51
Italy 800182592
Access Code: 2155402
Updated by Bayes, Ryan over 8 years ago ยท 8 revisions