RunPlan20150611 » History » Version 1
Blackmore, Victoria, 11 June 2015 18:34
1 | 1 | Blackmore, Victoria | h1. June 11th, 2015 (Evening Run) |
---|---|---|---|
2 | |||
3 | *Aim:* Calibrating TOFs, testing Run Control, testing Online Reconstruction |
||
4 | |||
5 | |||
6 | h3. Daily schedule |
||
7 | |||
8 | | June | 11th | |
||
9 | |Time | 9pm - 5am | |
||
10 | | MOM | V. Blackmore | |
||
11 | | Lead shifter | S. Middleton | |
||
12 | | Shifter 2 | J. Nugent | |
||
13 | | BLOC | A. Dobbs | |
||
14 | | SOC | A. Dobbs | |
||
15 | | Experimenter | A. Dobbs, P. Hanlet | |
||
16 | | Physics Shifter | P. Franchini | |
||
17 | | | | | |
||
18 | | Beam? | Yes | |
||
19 | | Additional Personnel | | | |
||
20 | |||
21 | |||
22 | h2. Shift plan: |
||
23 | |||
24 | * 7:30pm |
||
25 | ** Shifters + BLOC arrive |
||
26 | ** Hall and beam line to be closed and prepared for beam |
||
27 | * 9pm |
||
28 | ** Check TOF1 response channel-by-channel |
||
29 | ** Operate experiment via Run Control, take data through to TOF2/KL/EMR to test Online Reconstruction |
||
30 | ** Settings as A. Dobbs requires |
||
31 | |||
32 | |||
33 | h2. Data Requested |
||
34 | |||
35 | * No data requested |
||
36 | |||
37 | |||
38 | h2. Beamline Configurations |
||
39 | |||
40 | * We expect to run with 2V beamloss and the beam bump active. |
||
41 | * DS is currently off |
||
42 | * Beam settings via Run Control |
||
43 | ** TOF1 calibration, short runs for Run Control testing |
||
44 | ** TOF1 calibration, long 100k triggers run -- aim for 1000 triggers/pixel |
||
45 | ** TOF0, TOF2 calibration, long 100k triggers runs (time permitting) |
||
46 | |||
47 | |||
48 | h2. Phone details for 6pm daily meeting |
||
49 | |||
50 | Phone access : ReadyTalk number |
||
51 | |||
52 | US 866-740-1260 |
||
53 | |||
54 | UK 0800-496-0576 |
||
55 | |||
56 | Swiss 0800-70-53-51 |
||
57 | |||
58 | Italy 800182592 |
||