June 7th, 2015¶
Aim: Prepare the upstream tracker for taking data, timing it with TOF0.
Daily schedule¶
June | 7th | |
Time | 4pm - 10pm | |
MOM | V. Blackmore | |
Lead shifter | J. Nugent | |
Shifter 2 | ||
BLOC | A. Dobbs | |
SOC | A. Dobbs | |
Experimenter | E. Overton, M. Uchida | |
Physics Shifter | P. Franchini | |
Beam? | Yes | |
Additional Personnel |
Shift plan:¶
- 2:30pm
- Shifters and BLOC arrive
- Close and secure Hall
- Prepare DAQ and Run Control for running
- Prepare Muon Beam Line for running
- 4pm
- Experts arrive.
- Run a pion beam of Ed & Melissa's choice (via Run Control) and figure out timing between ISIS, TOF0 and tracker
- 6pm
- Daily meeting:0800-496-0576, Access Code: 2155402
- Discuss timing progress and usefulness of evening run (without DS and given observed rates thus far)
- 10pm
- Change over to evening run
Data Requested¶
- Data to figure out tracker timing
- Data to test Run Control
Beamline Configurations¶
- We expect to run with 2V beamloss and the beam bump active.
- TOF1 is not in the beam line
- DS is currently off
- Begin with a pion beam from Run Control (e.g. as used for a TOF calibration) and adjust as instructed by E. Overton and M. Uchida
- Run Control testing between tracker data runs
Phone details¶
Phone access : ReadyTalk number
US 866-740-1260
UK 0800-496-0576
Swiss 0800-70-53-51
Italy 800182592
Access Code: 2155402
Updated by Blackmore, Victoria over 8 years ago ยท 2 revisions