RunPlan20150328 » History » Version 8

Karadzhov, Yordan, 26 March 2015 11:01

1 8 Karadzhov, Yordan
h1. Target commissioning + CKOV HV scan - 28th/29th March 2015
2 1 Boyd, Steven
3
h2. The purpose of the run is to:
4
5
* Get the system to a state where ToF (and CKOV) Calibration data can be taken
6
* Take some TOF calibration data 
7
8
h3. Daily schedule
9
10
| Date           | Saturday   | Saturday          |   Sunday      | Sunday     |  
11
| estimated time | 8am - 4pm    | 4 - 12pm        |  8am - 4pm    |  4pm - 12pm |
12
| MOM            | Y. Karadzhov | Y. Karadzhov    |  Y. Karadzhov | Y. Karadzhov   |
13
| Lead shifter   | P. Franchini | P. Hanlet       |  P. Frachini  | P. Hanlet       |
14 7 Boyd, Steven
| Shifter        | H. Nebrensky | P. Soler        |  H. Nebrensky | P. Soler | 
15 4 Boyd, Steven
| BLOC           |              |                 |               |                | 
16 1 Boyd, Steven
| SOC            |              |                 |               |                |
17
| Expert         |  Y Karadzhov (DAQ)|  | | |
18 2 Boyd, Steven
|                |              |                 |               |                | 
19
| Aim            | Take Data    |                 |               |                |
20
|                |              |                 |               |                |
21 5 Boyd, Steven
| Beam?          | Yes          | Yes             | Yes           | Yes            | 
22 6 Boyd, Steven
| Additional Personnel          |                 |               |                |  |
23 1 Boyd, Steven
24
h2. Prerequisites
25
26
"Run Preparation List":http://micewww.pp.rl.ac.uk/projects/operations/wiki/RunPreparationList
27
28
h2. Data Requested
29
30
h2. Beamline Configurations
31
32
* N.B. Decay Solenoid will not be available.
33
* We expect to be running with 2V beamloss and beam bump active.
34
35
h3. Preparation
36
37
* We will run beam into the hall so need to secure the MICE Hall
38
* Target needs to be ready
39
* BeamLine elements need to be ready
40
* Detectors need to be ready
41
* Controls needs to be ready
42
* DAQ needs to be ready
43
* OnMon and OnRec need to be ready
44
* Data Mover needs to be ready
45
46
h3. Shifter target training
47
48
* at shift handover on Saturday - somewhere between 15:00-17:00
49
50
h2. DAQ testing
51
52
* The main goal of this run is the commissioning of the new trigger system, which requires a calibration of the Time-of-flight system..
53
* We will take data with TOF0, TOF1 and Ckov. This means that we will use only one LDC (VME crate).
54
55
# We will start with a standalone readout of the TOF0/1 crate. This will be used for detecting eventual problems and debugging. The beam line will be set for Reference Run without Decay Solenoid.
56
# When we are satisfied with the quality of the data, we will switch to the original DAQ system and will take date for ~500 target pulses.
57
58
Reference Run without Decay Solenoid
59
60
| Particle Species| p at Tgt | p@D1| p@D2| p@Tof0 |Proton Absorber | Q1 | Q2 | Q3 | D1| DS | D2| Q4 | Q5 | Q6 | Q7 | Q8 | Q9 | Similar Run(s)|
61
|  | MeV/c |MeV/c |MeV/c | MeV/c | mm | A| A| A| A| A| A| A| A | A | A | A | A| DAQ run #|
62
|  pion| 272.42|268.67|265.98| 143.4| 29 | 57.8 | 105.6 | 64.6 | 202.8| ---| 100.4| 176.8 | 237.1| 157.2| 157.6| 238.5 | 203.7| 5729 |
63
64
h2. TOF calibration
65
66
# The beam line will be set for  TOF Calibration run
67
# The goal will be to take 30 000 target pulse or more.
68
69
h3. TOF Calibration run
70
71
| Number of pulses| Beamloss |  Particle Species| p at Tgt | p@D1| p@D2| Proton Absorber | Q1 | Q2 | Q3 | D1| DS | D2| Q4 | Q5 | Q6 | Q7 | Q8 | Q9 | Similar Run(s)|
72
| #  | V  | mm | A| A| A| A| A| A| A| A | A | A | A | A|A|A|A|A| DAQ run #|
73
| 30000 | 1 | Positron | 300.0 | 259.7 | 249.58 | 29  | 56.35 | 102.7 | 62.65 | 195.72| ---| 98.59| 163.16 |218.79 | 114.14| 83.40| 125.70 | 80.06| 1678 |
74
75
76
h2. Finish
77
78
* Shutdown target and re-open Hall for Monday