Target and Trigger timing + ToF calibration readiness - 28th/29th March 2015¶
The purpose of the run is to:¶
- Get the system to a state where ToF (and CKOV) Calibration data can be taken
- Take some TOF calibration data
Daily schedule¶
Date | Saturday | Saturday | Sunday | Sunday |
estimated time | 8am - 4pm | 4 - 12pm | 8am - 4pm | 4pm - 12pm |
MOM | Y. Karadzhov | Y. Karadzhov | Y. Karadzhov | Y. Karadzhov |
Lead shifter | P. Franchini | P. Hanlet | P. Frachini | P. Hanlet |
Shifter | P. Soler | ? | P. Soler | |
BLOC | H. Nebrensky | |||
SOC | ||||
Expert | Y Karadzhov (DAQ) | |||
Aim | Take Data | |||
Beam? | Yes | Yes | Yes | |
Additional Personnel |
Prerequisites¶
Data Requested¶
Beamline Configurations¶
- N.B. Decay Solenoid will not be available.
- We expect to be running with 2V beamloss and beam bump active.
Preparation¶
- We will run beam into the hall so need to secure the MICE Hall
- Target needs to be ready
- BeamLine elements need to be ready
- Detectors need to be ready
- Controls needs to be ready
- DAQ needs to be ready
- OnMon and OnRec need to be ready
- Data Mover needs to be ready
Shifter target training¶
- at shift handover on Saturday - somewhere between 15:00-17:00
DAQ testing¶
- The main goal of this run is the commissioning of the new trigger system, which requires a calibration of the Time-of-flight system..
- We will take data with TOF0, TOF1 and Ckov. This means that we will use only one LDC (VME crate).
- We will start with a standalone readout of the TOF0/1 crate. This will be used for detecting eventual problems and debugging. The beam line will be set for Reference Run without Decay Solenoid.
- When we are satisfied with the quality of the data, we will switch to the original DAQ system and will take date for ~500 target pulses.
Reference Run without Decay Solenoid
Particle Species | p at Tgt | p@D1 | p@D2 | p@Tof0 | Proton Absorber | Q1 | Q2 | Q3 | D1 | DS | D2 | Q4 | Q5 | Q6 | Q7 | Q8 | Q9 | Similar Run(s) |
MeV/c | MeV/c | MeV/c | MeV/c | mm | A | A | A | A | A | A | A | A | A | A | A | A | DAQ run # | |
pion | 272.42 | 268.67 | 265.98 | 143.4 | 29 | 57.8 | 105.6 | 64.6 | 202.8 | --- | 100.4 | 176.8 | 237.1 | 157.2 | 157.6 | 238.5 | 203.7 | 5729 |
TOF calibration¶
- The beam line will be set for TOF Calibration run
- The goal will be to take 30 000 target pulse or more.
TOF Calibration run¶
Number of pulses | Beamloss | Particle Species | p at Tgt | p@D1 | p@D2 | Proton Absorber | Q1 | Q2 | Q3 | D1 | DS | D2 | Q4 | Q5 | Q6 | Q7 | Q8 | Q9 | Similar Run(s) |
# | V | mm | A | A | A | A | A | A | A | A | A | A | A | A | A | A | A | A | DAQ run # |
30000 | 1 | Positron | 300.0 | 259.7 | 249.58 | 29 | 56.35 | 102.7 | 62.65 | 195.72 | --- | 98.59 | 163.16 | 218.79 | 114.14 | 83.40 | 125.70 | 80.06 | 1678 |
Finish¶
- Shutdown target and re-open Hall for Monday