RunPlan20150328 » History » Version 13
Heidt, Christopher, 29 March 2015 15:17
1 | 8 | Karadzhov, Yordan | h1. Target commissioning + CKOV HV scan - 28th/29th March 2015 |
---|---|---|---|
2 | 1 | Boyd, Steven | |
3 | h2. The purpose of the run is to: |
||
4 | |||
5 | * Get the system to a state where ToF (and CKOV) Calibration data can be taken |
||
6 | * Take some TOF calibration data |
||
7 | |||
8 | h3. Daily schedule |
||
9 | |||
10 | | Date | Saturday | Saturday | Sunday | Sunday | |
||
11 | | estimated time | 8am - 4pm | 4 - 12pm | 8am - 4pm | 4pm - 12pm | |
||
12 | | MOM | Y. Karadzhov | Y. Karadzhov | Y. Karadzhov | Y. Karadzhov | |
||
13 | | Lead shifter | P. Franchini | P. Hanlet | P. Frachini | P. Hanlet | |
||
14 | 7 | Boyd, Steven | | Shifter | H. Nebrensky | P. Soler | H. Nebrensky | P. Soler | |
15 | 4 | Boyd, Steven | | BLOC | | | | | |
16 | 11 | Boyd, Steven | | SOC | R. Bayes | R. Bayes | R. Bayes | R. Bayes | |
17 | 1 | Boyd, Steven | | Expert | Y Karadzhov (DAQ)| | | | |
18 | 2 | Boyd, Steven | | | | | | | |
19 | | Aim | Take Data | | | | |
||
20 | | | | | | | |
||
21 | 5 | Boyd, Steven | | Beam? | Yes | Yes | Yes | Yes | |
22 | 6 | Boyd, Steven | | Additional Personnel | | | | | |
23 | 1 | Boyd, Steven | |
24 | h2. Prerequisites |
||
25 | |||
26 | "Run Preparation List":http://micewww.pp.rl.ac.uk/projects/operations/wiki/RunPreparationList |
||
27 | |||
28 | h2. Data Requested |
||
29 | |||
30 | h2. Beamline Configurations |
||
31 | |||
32 | * N.B. Decay Solenoid will not be available. |
||
33 | * We expect to be running with 2V beamloss and beam bump active. |
||
34 | |||
35 | h3. Preparation |
||
36 | |||
37 | * We will run beam into the hall so need to secure the MICE Hall |
||
38 | * Target needs to be ready |
||
39 | * BeamLine elements need to be ready |
||
40 | * Detectors need to be ready |
||
41 | * Controls needs to be ready |
||
42 | * DAQ needs to be ready |
||
43 | * OnMon and OnRec need to be ready |
||
44 | * Data Mover needs to be ready |
||
45 | |||
46 | h3. Shifter target training |
||
47 | |||
48 | * at shift handover on Saturday - somewhere between 15:00-17:00 |
||
49 | |||
50 | h2. DAQ testing |
||
51 | |||
52 | * We will take data with TOF0, TOF1 and Ckov. This means that we will use only one LDC (VME crate). |
||
53 | 9 | Karadzhov, Yordan | * The main goal of this run is the continue with the commissioning of the new trigger system, and to investigate the stability issue found last weekend. |
54 | * We will start with the debugging of the the stability issue. This operation will require unspecified amount of time. |
||
55 | 1 | Boyd, Steven | |
56 | Reference Run without Decay Solenoid |
||
57 | |||
58 | 10 | Karadzhov, Yordan | | Number of pulses | Particle Species| p at Tgt | p@D1| p@D2| p@Tof0 |Proton Absorber | Q1 | Q2 | Q3 | D1| DS | D2| Q4 | Q5 | Q6 | Q7 | Q8 | Q9 | Similar Run(s)| |
59 | | # | | MeV/c |MeV/c |MeV/c | MeV/c | mm | A| A| A| A| A| A| A| A | A | A | A | A| DAQ run #| |
||
60 | | 1 000 | pion| 272.42|268.67|265.98| 143.4| 29 | 57.8 | 105.6 | 64.6 | 202.8| ---| 100.4| 176.8 | 237.1| 157.2| 157.6| 238.5 | 203.7| 5729 | |
||
61 | 1 | Boyd, Steven | |
62 | 10 | Karadzhov, Yordan | # The beam line will be first set for Reference Run without Decay Solenoid. |
63 | # Then we will continue with the Ckov momentum scan on the pion momentum |
||
64 | |||
65 | h2. CKOV momentum scan run |
||
66 | |||
67 | * We will do a momentum scan on the pion momentum. There should be enough statistics with only 2000 actuations each run. |
||
68 | * To be carried out simultaneously with the debugging of the stability issue. |
||
69 | |||
70 | | Number of pulses | Particle Species| p at Tgt | p@D1| p@D2|Proton Absorber | Q1 | Q2 | Q3 | D1| DS | D2| Q4 | Q5 | Q6 | Q7 | Q8 | Q9 | Similar Run(s)| |
||
71 | | # | | MeV/c |MeV/c |MeV/c | mm | A| A| A| A| A| A| A| A | A | A | A | A| DAQ run #| |
||
72 | | 2000 | pion| 300 |268.67|265.98| 29 | 57.8 | 105.6 | 64.6 | 202.8| ---| 100.4| 176.8 | 237.1| 157.2| 157.6| 238.5 | 203.7| 5729 | |
||
73 | | 2000 | pion| 325 |321.5|319| 83 | 69.1 |126.3 |77.31 | 246| ---| 119.6| 212.4| 284.8 | 188.9 | 193.7| 293.2 |250.6| 5439 | |
||
74 | | 2000 | pion| 350 |346.58 | 344.14 | 83 | 74.5 | 136.1 | 83.3| 267.7 | ---| 128.8| 229.2 | 307.4 | 204| 210.6 | 318.8 | 272.5 | 5444 | |
||
75 | | 2000 | pion| 375 |371.6 | 369.2 | 83 | 79.8 | 146 | 89.4 | 290.4 | ---| 137.9| 246 | 330 | 218.9| 227.3 | 344.1 | 294.2 | 5442 | |
||
76 | | 2000 | pion| 400 |396.7 | 394.3 | 83 | 85.2 | 155.8 | 95.4 | 314.3 | ---| 147.1| 262.8 | 352.5 | 233.9| 244 | 369.4 | 315.8 | 5440 | |
||
77 | | 2000 | pion| 425 |421.7 | 419.36 | 83 | 90.55 | 165.6 | 101.38 | 339.36 | ---| 156.26| 279.61 | 374.97 | 248.84| 260.49 | 394.43 | 337.23 | 5437 | |
||
78 | | |
||
79 | |||
80 | 9 | Karadzhov, Yordan | h2. TOF calibration by using the old trigger system. |
81 | 1 | Boyd, Steven | |
82 | 9 | Karadzhov, Yordan | * This calibration will be used for comparison New vs. Old Trigger |
83 | * The goal will be to take 30 000 target pulse or more. |
||
84 | * Trigger provided by the old Tr. system. |
||
85 | # The beam line will be set for TOF Calibration run. |
||
86 | |||
87 | h3. TOF Calibration run |
||
88 | |||
89 | | Number of pulses| Beamloss | Particle Species| p at Tgt | p@D1| p@D2| Proton Absorber | Q1 | Q2 | Q3 | D1| DS | D2| Q4 | Q5 | Q6 | Q7 | Q8 | Q9 | Similar Run(s)| |
||
90 | | # | V | mm | A| A| A| A| A| A| A| A | A | A | A | A|A|A|A|A| DAQ run #| |
||
91 | | 30000 | 1 | Positron | 300.0 | 259.7 | 249.58 | 29 | 56.35 | 102.7 | 62.65 | 195.72| ---| 98.59| 163.16 |218.79 | 114.14| 83.40| 125.70 | 80.06| 1678 | |
||
92 | |||
93 | 12 | Heidt, Christopher | h2. -CKOV HV scan run- |
94 | 9 | Karadzhov, Yordan | |
95 | * We also want to do a Ckov HV and momentum scan. |
||
96 | * To be carried out simultaneously and parasitically with the TOF calibration run on electron beam as shown above |
||
97 | * Previous run to be split into 5 runs with 5000 pulses each run, scanning in a range of +- 50 V around nominal settings for CKOV HV settings |
||
98 | |||
99 | | Run type | Number of pulses| CKOVa1 | CKOVa2 | CKOVa3 | CKOVa4 | CKOVb1| CKOVb2 | CKOVb3 | CKOVb4 | |
||
100 | | | # | V | V | V | V | V | V | V | V | |
||
101 | | Default CKOV HV | 5000 | 1610 | 1520 | 1570 | 1625 | 1540 | 1590 | 1540 | 1495| |
||
102 | | Default CKOV HV - 50V | 5000 | 1560 | 1470 | 1520 | 1575 | 1490 | 1540 | 1490 | 1445| |
||
103 | | Default CKOV HV - 25V | 5000 | 1585 | 1495 | 1545 | 1600 | 1515 | 1565 | 1515 | 1470| |
||
104 | | Default CKOV HV + 25V | 5000 | 1635 | 1545 | 1595 | 1650 | 1565 | 1615 | 1565 | 1520| |
||
105 | | Default CKOV HV + 50V | 5000 | 1660 | 1570 | 1620 | 1675 | 1590 | 1640 | 1590 | 1545| |
||
106 | 1 | Boyd, Steven | |
107 | 13 | Heidt, Christopher | |
108 | h2. Q123 Scan |
||
109 | |||
110 | * We will take data with TOF0 and TOF1, however TOF0 is most important. |
||
111 | * The main goal of these operations is to investigate upstream beamline setting (Q1,Q2,Q3). In particular settings with lower current in Q1 are investigated. |
||
112 | * This activity will use the new calibrated trigger system. |
||
113 | |||
114 | |||
115 | Reference Run without Decay Solenoid + Runs with modified settings |
||
116 | |||
117 | | Run type | Number of pulses | Particle Species| p at Tgt | p@D1| p@D2| p@Tof0 |Proton Absorber | Q1 | Q2 | Q3 | D1| DS | D2| Q4 | Q5 | Q6 | Q7 | Q8 | Q9 | Similar Run(s)| |
||
118 | | | # | | MeV/c |MeV/c |MeV/c | MeV/c | mm | A| A| A| A| A| A| A| A | A | A | A | A| DAQ run #| |
||
119 | | Reference |500 | pion| 272.42|268.67|265.98| 143.4| 29 | 57.8 | 105.6 | 64.6 | 202.8| ---| 100.4| 176.8 | 237.1| 157.2| 157.6| 238.5 | 203.7| 5729 | |
||
120 | | Lower 1 |500 | pion| 272.42|268.67|265.98| 143.4| 29 | 57.8 | 105.6 | 64.6 | 202.8| ---| 100.4| 176.8 | 237.1| 157.2| 157.6| 238.5 | 203.7| 5729 | |
||
121 | | Lower 2 |500 | pion| 272.42|268.67|265.98| 143.4| 29 | 57.8 | 105.6 | 64.6 | 202.8| ---| 100.4| 176.8 | 237.1| 157.2| 157.6| 238.5 | 203.7| 5729 | |
||
122 | | Lower 3 |500 | pion| 272.42|268.67|265.98| 143.4| 29 | 57.8 | 105.6 | 64.6 | 202.8| ---| 100.4| 176.8 | 237.1| 157.2| 157.6| 238.5 | 203.7| 5729 | |
||
123 | | Lower 1a |500 | pion| 272.42|268.67|265.98| 143.4| 29 | 57.8 | 105.6 | 64.6 | 202.8| ---| 100.4| 176.8 | 237.1| 157.2| 157.6| 238.5 | 203.7| 5729 | |
||
124 | | Lower 2a |500 | pion| 272.42|268.67|265.98| 143.4| 29 | 57.8 | 105.6 | 64.6 | 202.8| ---| 100.4| 176.8 | 237.1| 157.2| 157.6| 238.5 | 203.7| 5729 | |
||
125 | | Refer 3a |500 | pion| 272.42|268.67|265.98| 143.4| 29 | 57.8 | 105.6 | 64.6 | 202.8| ---| 100.4| 176.8 | 237.1| 157.2| 157.6| 238.5 | 203.7| 5729 | |
||
126 | |||
127 | |||
128 | 1 | Boyd, Steven | h2. Finish |
129 | |||
130 | * Shutdown target and re-open Hall for Monday |