Actions
Run Plan 2015/01/15 Controls Status¶
Following discussion between Chris Rogers, Pierrick Hanlet 10:00 on Tuesday 6th January
Summary¶
- Beamline ioc -> finished but problems with integration tests (due to external issues)
- Beamline state machine -> in progress, due Friday 9th Jan
- Run control -> not started, no estimate for completion
- Tracker -> in progress; critical issue is that SVS VME card has been replaced with a CAEN VME card; cannot at present control this even in standalone mode.
- EMR -> in progress
- Possible issue with SY527 (TOF HV)
Beamline¶
- Beamline ioc
- Coding work is complete
- PPS issue prevented operation of dipoles; bobs were not resetting; hence integration test failed
- Beamline state machine
- This week maybe
- Run control
- Not started don't know
- Diffuser state machine is near test
- Diffuser run control is in progress
Fall back on beamline is to run as standalone systems, controlled from the MLCR
Detectors¶
- EMR is challenging to complete
- missing a LV power supply in the hall, one is currently installed
- HV control is done
- LV control is in progress
- VME control is in progress
- NIM monitoring is in progress
- Rack switch is in progress
- temp monitoring - wrong monitors installed, monitoring unlikely to be available in near term
- Tracker
- Required new fibre runs, VME issues
- To run CAEN, need to integrate infrastructure IOC, tracker initialisation, Hanlet monitoring IOC, control IOC
- Plan to merge control IOC with Hanlet monitoring IOC
- Significant risk to tracker operation
- Alan Bross, Paul Rubinov arriving on 15th Jan to 24th Jan
(Shifter training Feb)¶
- Chris Heidt will be in charge of the training for the C+M shifter training
Updated by Rogers, Chris almost 9 years ago ยท 2 revisions