Mock data run

Wednesday 21st January 2015

Systems

System Expert Arrival Departure Docs Status
Beamline
PPS Craig MacWaters Local ok Update, 2015-01-08, Main door won't close!
Target Henry Nebrensky Local ok RunPlan20150115_Beamline_Status
Decay Sol Chris White/Henry 12th January 16th January ok RunPlan20150115_Beamline_Status
NC Magnets Henry Nebrensky Local ok RunPlan20150115_Beamline_Status
Beamstop Henry Nebrensky Local ok RunPlan20150115_Beamline_Status
Proton Abs (Henry Nebrensky) Local no RunPlan20150115_Beamline_Status
Diffuser Pierrick Hanlet Local no Hardware okay; state machine and run control need further work
Detectors
TOF SY527 won't run on remote in SL6.4 ok
Tracker David Adey RunPlan20150115_Tracker_Status
KL
EMR Yordan Karadzhov, Francois Drielsma 12th January 15th January RunPlan20150115_EMR_Status
Ckov Pierrick Hanlet Local
LM
DAQ
Tracker DAQ David Adey Now > 21st January RunPlan20150115_Tracker_Status
PID DAQ Yordan Karadzhov 12th January 14th January InfoBrowser is freezing up
Old Trigger Yordan Karadzhov 12th January 14th January
New Trigger Yordan Karadzhov 12th January 14th January
Computing
Controls Pierrick Hanlet Local RunPlan20150115_Controls_Status
MLCR Servers Ed Overton 12th January 23rd January
Datamover Janusz Martyniak 21st 21st ok
Online Recon Adam Dobbs Local Needs meeting with Dobbs
Online Monitoring Rhys Gardener 12th January

Prerequisites

20150115_RunPreparationList

Preparations

Representatives from each sub-detector must be available and present at
RAL to ensure that their systems are running properly during the week before this test.
During this week will do individual tests of each of the systems. I think, then,
that we should reserve a day for each of the subdetectors to make certain that they can
interface with C&M, and are ready to be placed into the full integrated test. A preliminary plan is

12th January Ensure that the trigger is ready, the control room systems are up and running and the controls are ready
13th January Test TOF
14th January Test KL
15th January Test EMR
16th January Test Tracker readout
19th January Test beamline and beamline controls
20th January Spare day
21st January Full system test

Run Plan

Name Target Frame Proton Absorber Beam Stop Diffuser Q1 Q2 Q3 D1 DS D2 Q4 Q5 Q6 Q7 Q8 Q9 Trigger Time
bitmask bitmask A A A A A A A A A A A A mins
Test 1 Lowered 0000 Closed 0000 102.4 127.9 89 323.2 669 94.2 158.1 212 140.6 138.7 209.8 179.2 New, TOF1 30
Test 2 Lowered 1111 Closed 1111 184.4 101.2 112.6 387.9 200.0 167.7 295.0 395.6 260.9 197.8 298.4 253.52 New, TOF1 30
Test 3 Lowered 0000 Closed 0000 102.4 127.9 89 323.2 669 94.2 158.1 212 140.6 138.7 209.8 179.2 New, TOF0 10
Test 4 Lowered 0000 Closed 0000 102.4 127.9 89 323.2 669 94.2 158.1 212 140.6 138.7 209.8 179.2 New, TOF1 10
Test 5 Lowered 0000 Closed 0000 102.4 127.9 89 323.2 669 94.2 158.1 212 140.6 138.7 209.8 179.2 New, TOF1, internal tracker LED pulsers 10
Test 6 Lowered 0000 Closed 0000 102.4 127.9 89 323.2 669 94.2 158.1 212 140.6 138.7 209.8 179.2 New, TOF1, external tracker LED pulsers 30
Test 7 Lowered 0000 Closed 0000 102.4 127.9 89 323.2 669 94.2 158.1 212 140.6 138.7 209.8 179.2 Old, TOF0 30
Test 8 Lowered 0000 Closed 0000 102.4 127.9 89 323.2 669 94.2 158.1 212 140.6 138.7 209.8 179.2 Old, TOF1 10
Test 9 Lowered 0000 Closed 0000 102.4 127.9 89 323.2 669 94.2 158.1 212 140.6 138.7 209.8 179.2 Old, TOF1, internal tracker LED pulsers 10
Test 10 Lowered 0000 Closed 0000 102.4 127.9 89 323.2 669 94.2 158.1 212 140.6 138.7 209.8 179.2 Old, TOF1, external tracker LED pulsers 10
  • Aim of rotating the trigger is to check readout of each TOF detector with old and new trigger. Should be possible to at least check up to e.g. slab hits or uncalibrated space points this way.
    • Sounds like TOF2 cannot be dealt with in this way.
  • Add in tracker LED pulsers to check that tracker is reading out okay with trigger system. This checks that the tracker is timed in correctly with the TOF1 trigger. Probably only want to check timing with TOF1 trigger. Question do we want to implement timing with other triggers?
  • Note this will not check some of Ckov, KL, EMR systems.

Beamline test

  • Try running C+M against production CDB
  • Check to see if C+M is updating CDB okay
  • Dip target enough times that the temperature is stable, say half an hour of dipping
  • Run a couple of settings
  • Insert all proton absorbers and no proton absorbers
  • Insert all diffuser and no diffuser

Detector and DAQ test

  • Power all detectors
  • Power DAQ with new trigger, then old trigger (new trigger is priority now)
  • Run online monitoring
  • Run online reconstruction
  • Check that online monitoring observes triggers from all detectors incl. tracker
  • Check that online reconstruction reconstructs data correctly
  • Check that data mover moves data to GRID and offline reconstruction goes

Updated by Overton, Edward over 8 years ago ยท 106 revisions