Mock data run¶
Wednesday 21st January 2015
Systems¶
System | Expert | Arrival | Departure | Docs | Status |
Beamline | |||||
PPS | Craig MacWaters | Local | ok | Update, 2015-01-08, Main door won't close! | |
Target | Henry Nebrensky | Local | ok | RunPlan20150115_Beamline_Status | |
Decay Sol | Chris White/Henry | 12th January | 16th January | ok | RunPlan20150115_Beamline_Status |
NC Magnets | Henry Nebrensky | Local | ok | RunPlan20150115_Beamline_Status | |
Beamstop | Henry Nebrensky | Local | ok | RunPlan20150115_Beamline_Status | |
Proton Abs | (Henry Nebrensky) | Local | no | RunPlan20150115_Beamline_Status | |
Diffuser | Pierrick Hanlet | Local | no | Hardware okay; state machine and run control need further work | |
Detectors | |||||
TOF | |
||||
Tracker | David Adey | RunPlan20150115_Tracker_Status | |||
KL | |||||
EMR | Yordan Karadzhov, Francois Drielsma | 12th January | 15th January | RunPlan20150115_EMR_Status | |
Ckov | Pierrick Hanlet | Local | |||
LM | |||||
DAQ | |||||
Tracker DAQ | David Adey | Now | > 21st January | RunPlan20150115_Tracker_Status | |
PID DAQ | Yordan Karadzhov | 12th January | 14th January | InfoBrowser is freezing up | |
Old Trigger | Yordan Karadzhov | 12th January | 14th January | ||
New Trigger | Yordan Karadzhov | 12th January | 14th January | ||
Computing | |||||
Controls | Pierrick Hanlet | Local | RunPlan20150115_Controls_Status | ||
MLCR Servers | Ed Overton | 12th January | 23rd January | ||
Datamover | Janusz Martyniak | 21st | 21st | ok | |
Online Recon | Adam Dobbs | Local | Needs meeting with Dobbs | ||
Online Monitoring | Rhys Gardener | 12th January |
Prerequisites¶
Preparations¶
Representatives from each sub-detector must be available and present at
RAL to ensure that their systems are running properly during the week before this test.
During this week will do individual tests of each of the systems. I think, then,
that we should reserve a day for each of the subdetectors to make certain that they can
interface with C&M, and are ready to be placed into the full integrated test. A preliminary plan is
12th January | Ensure that the trigger is ready, the control room systems are up and running and the controls are ready |
13th January | Test TOF |
14th January | Test KL |
15th January | Test EMR |
16th January | Test Tracker readout |
19th January | Test beamline and beamline controls |
20th January | Spare day |
21st January | Full system test |
Run Plan¶
Name | Target Frame | Proton Absorber | Beam Stop | Diffuser | Q1 | Q2 | Q3 | D1 | DS | D2 | Q4 | Q5 | Q6 | Q7 | Q8 | Q9 | Trigger | Time |
bitmask | bitmask | A | A | A | A | A | A | A | A | A | A | A | A | mins | ||||
Test 1 | Lowered | 0000 | Closed | 0000 | 102.4 | 127.9 | 89 | 323.2 | 669 | 94.2 | 158.1 | 212 | 140.6 | 138.7 | 209.8 | 179.2 | New, TOF1 | 30 |
Test 2 | Lowered | 1111 | Closed | 1111 | 184.4 | 101.2 | 112.6 | 387.9 | 200.0 | 167.7 | 295.0 | 395.6 | 260.9 | 197.8 | 298.4 | 253.52 | New, TOF1 | 30 |
Test 3 | Lowered | 0000 | Closed | 0000 | 102.4 | 127.9 | 89 | 323.2 | 669 | 94.2 | 158.1 | 212 | 140.6 | 138.7 | 209.8 | 179.2 | New, TOF0 | 10 |
Test 4 | Lowered | 0000 | Closed | 0000 | 102.4 | 127.9 | 89 | 323.2 | 669 | 94.2 | 158.1 | 212 | 140.6 | 138.7 | 209.8 | 179.2 | New, TOF1 | 10 |
Test 5 | Lowered | 0000 | Closed | 0000 | 102.4 | 127.9 | 89 | 323.2 | 669 | 94.2 | 158.1 | 212 | 140.6 | 138.7 | 209.8 | 179.2 | New, TOF1, internal tracker LED pulsers | 10 |
Test 6 | Lowered | 0000 | Closed | 0000 | 102.4 | 127.9 | 89 | 323.2 | 669 | 94.2 | 158.1 | 212 | 140.6 | 138.7 | 209.8 | 179.2 | New, TOF1, external tracker LED pulsers | 30 |
Test 7 | Lowered | 0000 | Closed | 0000 | 102.4 | 127.9 | 89 | 323.2 | 669 | 94.2 | 158.1 | 212 | 140.6 | 138.7 | 209.8 | 179.2 | Old, TOF0 | 30 |
Test 8 | Lowered | 0000 | Closed | 0000 | 102.4 | 127.9 | 89 | 323.2 | 669 | 94.2 | 158.1 | 212 | 140.6 | 138.7 | 209.8 | 179.2 | Old, TOF1 | 10 |
Test 9 | Lowered | 0000 | Closed | 0000 | 102.4 | 127.9 | 89 | 323.2 | 669 | 94.2 | 158.1 | 212 | 140.6 | 138.7 | 209.8 | 179.2 | Old, TOF1, internal tracker LED pulsers | 10 |
Test 10 | Lowered | 0000 | Closed | 0000 | 102.4 | 127.9 | 89 | 323.2 | 669 | 94.2 | 158.1 | 212 | 140.6 | 138.7 | 209.8 | 179.2 | Old, TOF1, external tracker LED pulsers | 10 |
- Aim of rotating the trigger is to check readout of each TOF detector with old and new trigger. Should be possible to at least check up to e.g. slab hits or uncalibrated space points this way.
- Sounds like TOF2 cannot be dealt with in this way.
- Add in tracker LED pulsers to check that tracker is reading out okay with trigger system. This checks that the tracker is timed in correctly with the TOF1 trigger. Probably only want to check timing with TOF1 trigger. Question do we want to implement timing with other triggers?
- Note this will not check some of Ckov, KL, EMR systems.
Beamline test¶
- Try running C+M against production CDB
- Check to see if C+M is updating CDB okay
- Dip target enough times that the temperature is stable, say half an hour of dipping
- Run a couple of settings
- Insert all proton absorbers and no proton absorbers
- Insert all diffuser and no diffuser
Detector and DAQ test¶
- Power all detectors
- Power DAQ with new trigger, then old trigger (new trigger is priority now)
- Run online monitoring
- Run online reconstruction
- Check that online monitoring observes triggers from all detectors incl. tracker
- Check that online reconstruction reconstructs data correctly
- Check that data mover moves data to GRID and offline reconstruction goes