Run Plan 3rd - 7th October 2013

Commissioning run for the EMR detector.

Goals of the run:
The primary goal of the run is to commission the EMR, taking data necessary for calibration, ranging studies and PID studies.

MICE will aim to run for three weekends in a row. The desired studies are subdivided by weekend, but will shift to the next weekend if not completed. The initial plan is:

  • 2013/10/03 - 2013/10/07
    • Start Thursday lunch time (13:00), search MICE Hall and close.
    • Set trigger to TOF2.
    • Maximize beam rate; positive "pion" beam at 350 MeV/c or higher.
    • Maximum positive "muon" beam.
    • Attempt negative "pion" beam.
  • 2013/10/10 - 2013/10/14
    • Start Thursday lunch time (13:00), search MICE Hall and close.
    • Confirm trigger set to TOF2.
    • Repeat and/or correct any runs from previous weekend.
    • Positive Pion beam, start scan of momentum to cover momentum range where muons stop in the EMR, and higher.
  • 2013/10/17 - 2013/10/21
    • Start Thursday lunch time (13:00), search MICE Hall and close.
    • Confirm trigger set to TOF2.
    • Repeat and/or correct any runs from previous weekend.
    • Switch to negative polarity or muon beam, test additional presence of electrons.
    • Take as much electron data as possible.

Shift Schedule:

Shifter hours of service:

  • Thursday:
    • MOM, Shifter * 2, BLOC:
      • 13:00 - 20:00
  • Friday - Monday:
    • MOM:
      • 08:00 - 10:00
      • 18:00 - 20:00
    • Lead Shifter:
      • 10:00 - 18:00
    • Shifter 1:
      • 08:00 - 16:00
    • Shifter 2:
      • 12:00 - 20:00

Daily schedule

October 3 4 5 6 7
Estimated time 13:00 - 20:00 08:00 - 20:00 08:00 - 20:00 08:00 - 20:00 08:00 - 20:00
MOM R. Bayes R. Bayes R. Bayes R. Bayes R. Bayes
Lead shifter ######## IT / HN (a) IT / HN (a) A. Dobbs A. Dobbs
Shifter 1 I. Taylor Y. Karadzhov Y. Karadzhov F. Drielsma F. Drielsma
Shifter 2 C. Pidcott S. Ricciardi V. Verguilov V. Verguilov V. Verguilov
BLOC HN / EO EO EO EO EO / PH?
SOC See Below See Below See Below See Below See Below
Experimenter EMR Group EMR Group EMR Group EMR Group EMR Group
Aim Secure Hall Data taking Data taking Data taking Data taking
Data Taking
Beam? Yes Yes Yes Yes Yes
Training YK/VV/FD/RA YK/VV/FD/RA R. Asfandiyarov R. Asfandiyarov R. Asfandiyarov

Ruslan will serve as an extra shifter, to ensure he has the three shift credits required to serve as shift leader on the 13th and 14th.

(a) As Ryan is not a fully qualified lead shifter, Ian Taylor and Henry Nebrensky will provide cover as Lead Shifters on the 4th and 5th. Ian will attend from 08:00 - 14:00; Henry from 14:00 - 20:00.

Ryan Bayes will ensure that all shifters have an access card for R5.4, where the Target Vacuum Rack is stored, and that they are aware of the procedure for removing the target key, if instructed to do so by a BLOC.

October 10 11 12 13 14
Estimated time 13:00 - 20:00 08:00 - 20:00 08:00 - 20:00 08:00 - 20:00 08:00 - 20:00
MOM R. Bayes R. Bayes R. Bayes R. Bayes R. Bayes
Lead shifter ######## I. Taylor Y. Karadzhov R. Asfandiyarov R. Asfandiyarov
Shifter 1 J. Nugent Y. Karadzhov C. Hunt C. Hunt C. Hunt
Shifter 2 V. Verguilov J. Nugent J. Nugent V. Verguilov V. Verguilov
BLOC HN / PS PS PS PS PS
SOC See Below See Below See Below See Below See Below
Experimenter EMR Group EMR Group EMR Group EMR Group EMR Group
Aim Secure Hall Data taking Data taking Data taking Data taking
Data Taking
Beam? Yes Yes Yes Yes Yes
Training
October 17 18 19 20 21
Estimated time 13:00 - 20:00 08:00 - 20:00 08:00 - 20:00 08:00 - 20:00 08:00 - 20:00
MOM R. Bayes R. Bayes R. Bayes R. Bayes R. Bayes
Lead shifter ######## R. Gamut R. Gamut R. Gamut R. Gamut
Shifter 1 F. Drielsma P. Kyberd P. Kyberd S. Middleton S. Middleton
Shifter 2 C. Pidcott R. Gardner R. Gardner R. Gardner R. Asfandiyarov
BLOC HN EO / HN EO / HN EO / HN EO / IT
SOC See Below See Below See Below See Below See Below
Experimenter EMR Group EMR Group EMR Group EMR Group EMR Group
Aim Secure Hall Data taking Data taking Data taking Data taking
Data Taking
Beam? Yes Yes Yes Yes Yes
Training E. Noah E. Noah
October 24 25 26 27 28
Estimated time 13:00 - 20:00 08:00 - 20:00 08:00 - 20:00 08:00 - 20:00 08:00 - 20:00
MOM R. Bayes R. Bayes R. Bayes R. Bayes R. Bayes
Lead shifter ####### Y. Karadzhov Y. Karadzhov P. Hanlet P. Hanlet
Shifter 1 F. Drielsma C. Rogers F. Drielsma F. Drielsma F. Drielsma
Shifter 2 E. Noah E. Noah E. Noah E. Noah E. Noah
BLOC HN / PH PH / AD AD AD / IT IT
SOC See Below See Below See Below See Below See Below
Experimenter EMR Group EMR Group EMR Group EMR Group EMR Group
Aim Secure Hall Data taking Data taking Data taking Data taking
Data Taking
Beam? Yes Yes Yes Yes Yes
Training EN (b)

(b) Etam will need to be trained in PPS at the start of this shift.

Volunteers

The following shifters have volunteered to date:

Name Qualified Lead Shifter Possibly BLOC? Dates available
Sophie Middleton No No ???
Chris Rogers No No 3 * 08:00 - 16:00, Mon or Fri not 28
Ian Taylor Yes Yes 3rd-7th, 24th-28th
Pierrick Hanlet Yes Yes 3rd-7th, 10-12th, 24-28th
Celeste Pidcott No No 3rd-7th, 17th-21st, 24-28th
Rhys Gardener No No 18th-21st, maybe 11th-14th
John Nugent No No 3rd-7th, 10th-14th
Vassil Verguilov No (Untrained) No 3rd-7th, 10th-14th
Etam Noah No (Untrained) No 20th-21st, 24th, 28th
Paul Kyberd No No 11-12th, 18-19th, 25-27th
S. Ricciardi No No 4-7th
Chris Hunt No No 12-14th, 19th-21st, 26-28th
EMR Group Members No (Untrained) No Unset

SOC Shifts

Shift Thursday Friday Saturday Sunday Monday
03 - 07 October
8AM-2PM BST
2AM-8AM CDT
Ian Taylor Ed Santos Ed Santos Ed Santos
03 - 07 October
2PM-8PM BST
8AM-2PM CDT
Ian Taylor (1PM-8PM) Ed Santos Ed Santos Ed Santos Peter Lane
10 - 14 October
8AM-2PM BST
2AM-8AM CDT
Chris Rogers Ian Taylor Durga Rajaram Durga Rajaram
10 - 14 October
2PM-8PM BST
8AM-2PM CDT
Chris Rogers (1PM-8PM) Chris Rogers Peter Lane Peter Lane Peter Lane
17 - 21 October
8AM-2PM BST
2AM-8AM CDT
Durga Rajaram Ian Taylor Ian Taylor Chris Rogers
17 - 21 October
2PM-8PM BST
8AM-2PM CDT
Chris Rogers (1PM-8PM) Peter Lane Peter Lane Peter Lane Chris Rogers
24 - 28 October
8AM-2PM BST
2AM-8AM CDT
Durga Rajaram Ian Taylor Durga Rajaram Ian Taylor
24 - 28 October
2PM-8PM BST
8AM-2PM CDT
Chris Rogers (1PM-8PM) Durga Rajaram Durga Rajaram Ian Taylor Durga Rajaram

Data Requested

  • TBC

Beamline Configurations

We expect to be running with ?V beamloss and beam bump active. The Decay Solenoid will be off.

Further details to follow.

Data for Study 2:

Particle Species p at Tgt p@D1 p@D2 p@Tof0 Proton Absorber Q1 Q2 Q3 D1 DS D2 Q4 Q5 Q6 Q7 Q8 Q9 Ran? Similar Run(s)
MeV/c MeV/c MeV/c MeV/c mm A A A A A A A A A A A A DAQ run #
pion 430 ? ? ? 83 91.62 167.56 102.58 297 --- 158.12 282.96 379.47 251.83 263.79 399.44 341.52 4573
pion 430 ? ? ? 83 91.62 167.56 102.58 320 --- 158.12 282.96 379.47 251.83 263.79 399.44 341.52 4574