Project

General

Profile

RunPlan20130915 » History » Version 11

Nebrensky, Henry, 05 September 2013 14:54

1 1 Nebrensky, Henry
h1. BLOC training 15 September 2013
2
3
This is a training/revision session for BLOCs.
4 2 Nebrensky, Henry
Anyone who has not gone through the revised [[BLOCtraining|training schedule]] cannot act as BLOC in the upcoming run.
5 1 Nebrensky, Henry
6
I know it's an awkward date - but that's the only time we could get.
7
8 9 Nebrensky, Henry
h3. Attendees -(N.B. max. 6 in MLCR)
9 10 Nebrensky, Henry
10 9 Nebrensky, Henry
* Ed Overton
11
* Henry Nebrensky
12
* Pierrick Hanlet
13
* Ian Taylor
14
15 11 Nebrensky, Henry
h2. Advanced Target & PPS training session 
16 1 Nebrensky, Henry
17
h3. PPS (I) - 9:00
18
19
Will run target with Muon Test permit, will cover how to start setting up PPS without mimic.
20
21
h3. Target Theory - 9:30
22
23
0)  a) How the target works (explanation by poster)
24
    b) Control systems and Vac Rack (inc. access)
25
    c) Walkabout checklist items
26
27
1) a) Target powerup (can be done with frame raised)
28
     b) Basic (shifter-level) operation
29
     c) Monitoring plots and reports
30
     d) Checking the Target is operating to the correct spill (can be done with frame raised)
31
     e) Checking the beambump is active
32
     f) PPS interlocks; PPS vs BPS, etc.
33
     g) MICE Controlled Entry procedure
34
35
h3. Dipping into ISIS - 10:00 
36
37
2) a) Finding the ISIS Beam
38
     b) Checking the next spill injection losses (i.e. setting too long or short user delay).
39
     c) Optimising timing (playing with user delay to optimise beam loss profile)  Intrusive / Requires help from ISIS:
40
41
h3. "Intrusive" activities - 11:30
42
43
3) Running without the beambump (and how it changes everything!)
44
     Needs ISIS to turn off beambump temporarily
45
46
4) a) Overview of ISIS BLMs and trips (minor vs major, I forget the terminology)
47
        Would it be possible to get this from Dean Adams or ISIS directly?
48
     b) Run at the margin to try to see some of the minor trips (this would
49
        be better done with the beamloss limit reduced to say 1V to reduce
50
        jitter)
51
52
5) Example of a BPS Trip (and what to do!)
53
54
h2. Magnets - cooling water etc. - after lunch
55 3 Nebrensky, Henry
56 8 Nebrensky, Henry
For future reference, _some of this_ would be done better during the shutdown.
57 7 Nebrensky, Henry
The following probably isn't in chronological order:
58 4 Nebrensky, Henry
59 3 Nebrensky, Henry
h3. Hall A/C Units
60
61
    * Turning on/off
62
63
h3. Decay Solenoid Cryo
64
65
    * Error messages
66
    * Air
67
68
h3. Proton Absorbers
69
70
    * _Cables/readout_
71
72
h3. Beamstop
73
74
    * Mechanical Beamstop removal/replacement
75
    * Swapping power packs
76
77
h3. Conventional / "Beamline" Magnets
78
79
    * Cooling water
80
    ** Temperatures
81
    ** Conductivity
82
    ** Turning off
83
    * Electricity
84
    ** Switch PSUs on/off
85
    ** PPS interlocks
86
    * Controls – VME PCs
87
    * POMPOMs
88
89
h3. Compressed Air
90
91
    * Receiver
92
    ** Purpose
93
    ** Monitoring
94
    * Booster
95
    ** Purpose
96
    ** Monitoring
97
98
h3. PPS (II)
99
100 4 Nebrensky, Henry
    * Which permits are needed for what
101 3 Nebrensky, Henry
    * Test Switch (location)
102
    * _DSA issues_
103
    * SC Magnet and other PPS featurettes
104
105
h3. Response procedure 
106
107
    * what to do when MLCR rings up in a panic...
108
109
h3. ISIS access
110
111
    * procedure and requirements
112
    * geography
113
114 6 Nebrensky, Henry
h3. Paperwork
115
116
* Open discussion of responsibility documents, shift rotas, etc.
117
118 3 Nebrensky, Henry
(aim is to finish before 16:00)