Run Plan - 2012-09-19

We will run for 16 hours only, probably sometime between 19th September to 21st September, TBC at ISIS schedule meeting on 5th September.

  1. Check target vs ISIS activation in beam bump mode
    • 8 hours ISIS off
    • Health physics/ISIS Crew perform activation measurement
    • 14 hours MICE target on with beam bump running @ 4V
    • 8 hours ISIS off
    • Health physics/ISIS Crew perform activation measurement
  2. Secondary aim - test online operation okay
    • Test upgrade of DAQ system/DATE
    • Test upgrade of online recon to 64 bit
    • Test reconstruction of TOF
    • Test reconstruction of Ckov
    • Test new UI in online recon
September Wed 19 Thur 20 Fri 21
MOM Coney Coney Coney
Lead shifter
Shifter 2
Shifter 3
Shifter 4
BLOC
SOC See Below See Below See Below

Shifter hours of service:

SOC Shifts

Time Zone US
Shift 1
UK
Shift 1
US
Shift 2
UK
Shift 2
US
Shift 3
UK
Shift 3
US
Shift 4
UK
Shift 4
US
Shift 5
UK
Shift 5
US
Shift 6
UK
Shift 6
BST 12AM-6AM 19 Sep 6AM-12PM 12PM-6PM 6PM-12AM 12AM-6AM 20 Sep 6AM-12PM 12PM-6PM 6PM-12AM 12AM-6AM 21 Sep 6AM-12PM 12PM-6PM 6PM-12AM
CDT 6PM-12AM Sep 18 12AM-6AM Sep 19 6AM-12PM 12PM-6PM 6PM-12AM 12AM-6AM Sep 20 6AM-12PM 12PM-6PM 6PM-12AM 12AM-6AM Sep 21 6AM-12PM 12PM-6PM
Shifter Durga Rajaram Chris Rogers Chris Rogers Ed Santos Ed Santos Chris Rogers Chris Rogers Durga Rajaram Peter Lane Matt Littlefield Peter Lane Matt Littlefield

Trained shifters

Note: Lead Shifters may also act as the secondary shifter.
New personnel are welcome but must go through the training procedure before taking shifts.

  • Lead Shifter
    • Chris Heidt
    • Pierrick Hanlet
    • Ray Gamet
    • Maria Leonova
    • Henry Nebrensky
  • Shifter
    • Paul Kyberd
    • Matt Littlefield
    • Justin Christensen
    • Sio-Chong Lo
  • Partially Trained Personnel
    • Ed Overton
    • Edward Santos

Updated by Lane, Peter about 11 years ago ยท 10 revisions