Hall Task List Dec16Feb17¶
Tasks for Winter Shutdown 16th December 2016 to 14th february 2017¶
Hall¶
- Oxygen depletion sensor service
- Polarity sensor (POMPOMs) radiation damage test (sometime in 23rd-27th Jan.; needs PPS permit)
- Neutron Monitor
- Proton Absorber 29mm slab upper limit (DSA)
- Diffuser iris 4 - remove diffuser Fri 16th Dec 8am.
- Trench water system #1878 :
- Correct the trench heat exchanger plumbing?
- Water circuit trench heat exchanger - reverse primary flow direction.
- Water circuit from South west corner to trench - T into trench heat exchanger primary circuit
Code Updates C&M¶
Test Trim coil power supplies- SS magnet operational tutorials - practical
- Ramp commands to SSU M coils
- GUI updates - 'information only GUI for SS magnets for shifters'
Trench water variables into archiverin Services & Environment #1881- State Machines for Alarms and Archiving, for
- Target, #1896
- Beamline, #1880
- Services and Environment, #1881
- Computing: UPSs #1213 ; File Compactor, #1895 ; ...
- Macro 'code topology' documentation
- Magnet monitoring GUIs should be made shift friendly (no access to compressors etc..)
- Water pump GUI password protected, #1891
- micenet lockout #1399 by end Jan.
- Compressed air at Diffuser not reported in EPICS, #1888
Electrical¶
- PPS functional test - Wednesday 18th ?
- Trench water system #1878 :
- confirm cause of pump failure
- correct mixing valve control loop
- Conventional magnets
- Earth Leakage tests (inc. Q789 at magnet)
- Q2 power supply
- magnet Interlocks alarm is inoperative
- Pressure sensor for Boosted air, #1890
Detectors¶
- Firmware for EMR spare
- Target:
- New Target control PC (today)
- [Restart R78 target test facility and test T2; rebuild S3?] (tomorrow)
Updated by Whyte, Colin over 6 years ago ยท 32 revisions