Hall Task List Dec16Feb17

Tasks for Winter Shutdown 16th December 2016 to 14th february 2017

Hall

  • Oxygen depletion sensor service
  • Polarity sensor (POMPOMs) radiation damage test (sometime in 23rd-27th Jan.; needs PPS permit)
  • Neutron Monitor
  • Proton Absorber 29mm slab upper limit (DSA)
  • Diffuser iris 4 - remove diffuser Fri 16th Dec 8am.
  • Trench water system #1878 :
    • Correct the trench heat exchanger plumbing?
    • Water circuit trench heat exchanger - reverse primary flow direction.
  • Water circuit from South west corner to trench - T into trench heat exchanger primary circuit

Code Updates C&M

  • Test Trim coil power supplies
  • SS magnet operational tutorials - practical
    • Ramp commands to SSU M coils
    • GUI updates - 'information only GUI for SS magnets for shifters'
    • Trench water variables into archiver in Services & Environment #1881
    • State Machines for Alarms and Archiving, for
      • Target, #1896
      • Beamline, #1880
      • Services and Environment, #1881
      • Computing: UPSs #1213 ; File Compactor, #1895 ; ...
    • Macro 'code topology' documentation
    • Magnet monitoring GUIs should be made shift friendly (no access to compressors etc..)
    • Water pump GUI password protected, #1891
  • micenet lockout #1399 by end Jan.
  • Compressed air at Diffuser not reported in EPICS, #1888

Electrical

  • PPS functional test - Wednesday 18th ?
  • Trench water system #1878 :
    • confirm cause of pump failure
    • correct mixing valve control loop
  • Conventional magnets
    • Earth Leakage tests (inc. Q789 at magnet)
    • Q2 power supply
    • magnet Interlocks alarm is inoperative
  • Pressure sensor for Boosted air, #1890

Detectors

  • Firmware for EMR spare
  • Target:
    • New Target control PC (today)
    • [Restart R78 target test facility and test T2; rebuild S3?] (tomorrow)

Updated by Whyte, Colin over 6 years ago ยท 32 revisions