Early June Preliminary Run Plan

Subject to beam being available:

  • Tuesday 2nd June : Tracker not available, TOF1 not available
    • 7pm - 9pm
      • Close and secure Hall
      • Beam tuning
      • Make DAQ and Run Control ready for running
    • 9pm
      • Review meeting between MOM and experts. Decision made to cancel shift at this point.
    • If not cancelled, 10pm - 6am
      • Measurements : Jaroslaw's beam precommissioning (scan of Q1,Q2,Q3) --> 02 June 2015 beam settings
      • Shift may end early. In this case procedures to be discussed in daily meeting.
  • Wednesday 3rd June : Cancelled due to work on conventional magnet water sytem
  • Thursday 4th June : Tracker not available, TOF1 not available
    • 7pm - 9pm
      • Close and secure Hall
      • Make DAQ and Run Control ready for running
    • 10pm - 6am
      • Repeat or complete work from Tuesday
      • Shift may end early. In this case procedures to be discussed in daily meeting.
  • Friday 5th June : TOF1 in beam, tracker available
    • 7pm - 9pm
      • Close and secure Hall
      • Make DAQ and Run Control ready for running
    • 10pm - 6am
      • Repeat or complete work from Tuesday
      • Reference run with TOF1 trigger (start of shift)
      • TOF Calibration runs
      • Cerenkov/EMR momentum scans
      • Jaroslaw measurement interrupt
  • Saturday 6th June
    • Finish or repeat runs from Friday
    • Tracker commissioning : exact run plan will be discussed at daily meeting.