Early June Preliminary Run Plan¶
Subject to beam being available:
- Tuesday 2nd June : Tracker not available, TOF1 not available
- 7pm - 9pm
- Close and secure Hall
- Beam tuning
- Make DAQ and Run Control ready for running
- 9pm
- Review meeting between MOM and experts. Decision made to cancel shift at this point.
- If not cancelled, 10pm - 6am
- Measurements : Jaroslaw's beam precommissioning (scan of Q1,Q2,Q3) --> 02 June 2015 beam settings
- Shift may end early. In this case procedures to be discussed in daily meeting.
- 7pm - 9pm
- Wednesday 3rd June : Cancelled due to work on conventional magnet water sytem
- Thursday 4th June : Tracker not available, TOF1 not available
- 7pm - 9pm
- Close and secure Hall
- Make DAQ and Run Control ready for running
- 10pm - 6am
- Repeat or complete work from Tuesday
- Shift may end early. In this case procedures to be discussed in daily meeting.
- 7pm - 9pm
- Friday 5th June : TOF1 in beam, tracker available
- 7pm - 9pm
- Close and secure Hall
- Make DAQ and Run Control ready for running
- 10pm - 6am
- Repeat or complete work from Tuesday
- Reference run with TOF1 trigger (start of shift)
- TOF Calibration runs
- Cerenkov/EMR momentum scans
- Jaroslaw measurement interrupt
- 7pm - 9pm
- Saturday 6th June
- Finish or repeat runs from Friday
- Tracker commissioning : exact run plan will be discussed at daily meeting.