Actions
20180313¶
Location : MICE meeting room R1 2nd Floor East at 14:00 pm
VB, JG, PF, HN, PK, CW, AK, JB, KL
Phone access : phonebridge number
UK: 08082380274
US: 631.621.5253
Access code: 1779339517
- February jobs:
- Tracker:
- Cryostats have been disconnected. 1,2&3 ready to move. 4 trapped by vac lines. 3 Sumitomo systems stripped out.
- Helium window measurement - removed complete - move to tracker lab for metrology.
- Diffuser extracted (survey complete) -- and moved to tracker lab. Need to verify thickness and composition of the diffuser. (TM, CMcW)
- Target Controls test #1954 (Henry/Paolo 21st). Requires computers moving into Target rack - ongoing.
- D1 field.
- Limited plan from HN. as before - HN has spoken to Mike Krendler regarding removing pipe. D1 running would be end May.
- https://micewww.pp.rl.ac.uk/attachments/download/9660/2017-12-06_decommissioning-measurements_v3.pdf
- Document stands; no updates.
- Tracker:
- March jobs:
- SSU, SSD Magnet field map. 19th to 23rd March
- equipment delivered to R9 - move to MICE hall later in week.
- Cern team flights confirmed.
- first survey in place afternoon Mon 19th - TM advised.
- access passes for the CERN staff with Rose Hayes- complete?
- magnet settings desired
MICE_User_Run_2017_04_magnet_tests-v4.xls
- QPS test today
- SSU vacuum - north side turbo on - good vacuum?.
- hall search.
- SSU, SSD Magnet field map. 19th to 23rd March
- collaborator equipment return to power - in progress - new crates required- JG
- Next meeting - 20th Mar18.
- R9 empty by 19th.
- AOB.
- possible to search and lock Friday.
Updated by Nebrensky, Henry over 5 years ago · 9 revisions