h1. Ops/Comm Scheduling meeting : 23/5/2017
2
3
Location : CR21 at 14:00 pm
4
5
Phone access :  *New* phonebridge number
6
UK: 08082380274
7
US: 631.621.5253
8
Access code: 1779339517
9
10
h2. Agenda
11
12
* Actions
13
** -Macwaters - Re-make dodgy compressor2 remote cable connector - stands-
14
** Macwaters - Remove old overheated CSW71 to R9 _waiting for John Govans and the van_ - in progress
15 4 Boyd, Steven
** -Ajit - Implement MOM/DC state machine override function for all systems; also need documentation and training for operators - documentation and training in progress-
16 1 Boyd, Steven
** Macwaters - Report on status of FC psu repair (stands)
17
*** The spare is installed and has been run into a short 
18
** Hall Manager - water system change-over procedure (stands) - _collar people on Friday_
19
** EOverton - Status of @miceraid5@ disk cleanup (stands) _now has a script but needs to run it_
20
** Progress on Hall list  [[Hall_Task_List_Spring17|List of Hall activities in the shutdown]] (Colin) _DL were down on masse and made significant progress. Need to confirm if any remaining items_
21
** CWhyte to request survey of TOF1 - _requested, next week as Tony off this week_
22
** SBoyd to ensure we get updates on detector/data quality and on Target performance at Ops meetings
23
** AKurup to check which settings are being used by the active Alarm Handlers
24
** SBoyd to conscript extra shift cover for the end of next week : Done. Need BLOCs for the 31/1 and 2 of June (i.e. end of cycle)
25
26
* DC update
27
* MOM update
28 5 Rajaram, Durga
* Performance plots from TOF calibration run (Durga?) attachment:Onrec-9297.pdf
29 2 Boyd, Steven
* Update on the tracker saga
30 1 Boyd, Steven
* Hydrogen system update
31
* Run plan
32
** Tracker may be ready to operate on Friday
33
*** Is there still Helium in the tracker?
34
** LH2 running will not happen this cycle
35
** Extraction of LH2 absorber, re-insertion of the FC and establishment of the magnetic channel: Thursday (25May17)—Saturday (27May17);
36
** Magnet commissioning: Sunday (28May17)—Monday (29May17); and
37
** Empty-channel data taking (Monday 29May17)—Friday (02Jun17).
38 3 Boyd, Steven
** Last training date on Friday. I've asked shifters to meet the MOM on Friday to assess training plans. The MOM should set a time for this meeting.
39 1 Boyd, Steven
* AOB
40
41
* Last meeting : [[20170516|Tuesday May 9 2017]]
42
* Next meeting : [[20170530|Tuesday May 30 2017]] 
43 6 Nebrensky, Henry
44
h3. Minutes
45
46
* Actions
47
** Macwaters - Remove old overheated CSW71 to R9 _waiting for John Govans and the van_ - in progress
48
** Macwaters - Report on status of FC psu repair (stands)
49
*** The spare is installed and has been run into a short 
50
** Hall Manager - water system change-over procedure (stands) - _collar people on Friday_
51
** EOverton - Status of @miceraid5@ disk cleanup (stands) _now has a script but needs to run it_
52
** Progress on Hall list  [[Hall_Task_List_Spring17|List of Hall activities in the shutdown]] (Colin) _DL were down on masse and made significant progress. Need to confirm if any remaining items_
53
** CWhyte to request survey of TOF1 - _requested, due Thursday_ Removing absorber means will need to re-survey CC magnets after the User Cycle.
54
** SBoyd to ensure we get updates on detector/data quality and on Target performance at Ops meetings
55
** AKurup to check which settings are being used by the active Alarm Handlers
56
** SBoyd to conscript extra shift cover for the end of next week : Done. Need BLOCs for the 31/1 and 2 of June (i.e. end of cycle)
57
*** BLOCs at end of cycle will be shared between Ray and Henry. Note that both Tanaz and Ray/Henry are on day shift, so if they are called out during the night then MICE will need the stand-by shifter 
58
59
* New actions
60
** CWhyte to request survey of CC Magnets after cycle
61
** FDrielsma to investigate low-efficiency channels in EMR x-z
62
** Tracker group: decide what should be done to prevent repeat contamination of Tracker Cryostats  
63
64 7 Nebrensky, Henry
* DC update
65
  Work is on Hydrogen and Tracker: see below
66
67
* MOM update
68
  Ed starts as MOM tomorrow 
69
70 8 Nebrensky, Henry
* Target performance plots: see attachment:S19.pdf
71 7 Nebrensky, Henry
  Looks fine - leave it to carry on
72 8 Nebrensky, Henry
  
73 7 Nebrensky, Henry
* Performance plots from TOF calibration run (Durga): see attachment:Onrec-9297.pdf
74
  TOF0 - hope to get calibration in the 3 missing slots. TOF2 - waiting for re-calibration process to finish.
75 1 Boyd, Steven
  EMR has some low-efficiency channels in the x-z view right where the beam arrives - should investigate.
76 7 Nebrensky, Henry
77 9 Nebrensky, Henry
* DS fridge saga: Mark and Mike in mtg. with Joerg at the moment, deciding on threshold for remedial action
78 1 Boyd, Steven
79 9 Nebrensky, Henry
* Update on the tracker cryostat water ingress débâcle
80
  Have cooled cryostat 2 - "only" lost 20 channels. Have dried out cryostat 2 and are checking performance now. Cryostat 4 is cold, needs testing.
81
  Cryostat 1 has a leak into the cassette volume at the fibres. Appropriate sealant has been delivered and will be applied tomorrow when Craig is back. Should be cured on Thursday and will then start cooling.
82
  Possibly a batch of bad (i.e. wet) gas was the cause - need a plan to prevent repeat.
83
  Need to restart tracker volume helium flow on about Friday.
84
  We (Ed) still need to do the Tracker RF-timing alignment magic. 
85
  
86 1 Boyd, Steven
* Hydrogen system update
87 9 Nebrensky, Henry
  Managed to liquefy some Neon, but found some control system issues that caused circulation to stop.
88
  Should increase intensity of shifter monitoring? LH2 meeting at 15:00.
89
  Need to warm up on Thursday (to remove absorber) then close PRY. Have Geoff Barber and R12 staff on Thu and Fri, may need shifter assistance on Sat. NB no crane driver on Sat. 
90
91
* Run plan
92
** LH2 running will not happen this cycle
93
** Tracker may be ready to operate on Saturday
94
** Extraction of LH2 absorber, re-insertion of the FC and establishment of the magnetic channel: Thursday (25May17)—Saturday (27May17);
95
*** Need to get FC out of shorts and CC into flip modes 
96
** Magnet commissioning: Sunday (28May17)—Monday (29May17); and
97
** Empty-channel data taking (Monday 29May17)—Friday (02Jun17).
98
99
* AOB
100
** DSanders - still would like the wedge
101
** HNebrensky: would like to re-tune Beam-bump, need to fit round Hall work. Will contact Bryan.
102