Ops/Comm Scheduling meeting : 23/5/2017

Location : CR21 at 14:00 pm

Phone access : New phonebridge number
UK: 08082380274
US: 631.621.5253
Access code: 1779339517

Agenda

  • Actions
    • Macwaters - Re-make dodgy compressor2 remote cable connector - stands
    • Macwaters - Remove old overheated CSW71 to R9 waiting for John Govans and the van - in progress
    • Ajit - Implement MOM/DC state machine override function for all systems; also need documentation and training for operators - documentation and training in progress
    • Macwaters - Report on status of FC psu repair (stands)
      • The spare is installed and has been run into a short
    • Hall Manager - water system change-over procedure (stands) - collar people on Friday
    • EOverton - Status of miceraid5 disk cleanup (stands) now has a script but needs to run it
    • Progress on Hall list List of Hall activities in the shutdown (Colin) DL were down on masse and made significant progress. Need to confirm if any remaining items
    • CWhyte to request survey of TOF1 - requested, next week as Tony off this week
    • SBoyd to ensure we get updates on detector/data quality and on Target performance at Ops meetings
    • AKurup to check which settings are being used by the active Alarm Handlers
    • SBoyd to conscript extra shift cover for the end of next week : Done. Need BLOCs for the 31/1 and 2 of June (i.e. end of cycle)
  • DC update
  • MOM update
  • Performance plots from TOF calibration run (Durga?)
  • Update on the tracker saga
  • Hydrogen system update
  • Run plan
    • Tracker may be ready to operate on Friday
      • Is there still Helium in the tracker?
    • LH2 running will not happen this cycle
    • Extraction of LH2 absorber, re-insertion of the FC and establishment of the magnetic channel: Thursday (25May17)—Saturday (27May17);
    • Magnet commissioning: Sunday (28May17)—Monday (29May17); and
    • Empty-channel data taking (Monday 29May17)—Friday (02Jun17).