h1. Ops/Comm Scheduling meeting : 2/5/2017
2
3
Location : CR21 at 14:00 pm
4
5
Phone access :  *New* phonebridge number
6
UK: 08082380274
7
US: 631.621.5253
8
Access code: 1779339517
9
10
h2. Agenda
11
12
* Actions
13 9 Boyd, Steven
** -Macwaters & Boehm - Arrange to install new Sumitomo compressor adsorbers - stands-
14 1 Boyd, Steven
** Macwaters - Re-make dodgy compressor2 remote cable connector - stands
15 9 Boyd, Steven
** Macwaters - Remove old overheated CSW71 to R9. Speak to Sumitomo on April 5th regards how to repair. - in progress
16
** -Macwaters - Replace old vac sensors and new valve on cryo 1&2 - in progress-
17 1 Boyd, Steven
** Ajit - Implement MOM/DC state machine override function for all systems; also need documentation and training for operators - documentation and training in progress
18
** Macwaters - Report on status of FC psu repair (stands)
19
*** *This needs to be cross-checked* - e.g. Josef Boehm to check with Trevor. What is plan when it does return - will we want to test it _in situ_ before the run?
20 7 Boyd, Steven
*** _Josef :"we just run 50A through it when it is connected to the magnet"_ 
21 1 Boyd, Steven
** Hall Manager - water system change-over procedure (stands)
22
** EOverton - Status of @miceraid5@ disk cleanup (stands)
23
** JBoehm & Macwaters - get the West Wall compressors correctly labelled, as various have been re-purposed (stands)
24 9 Boyd, Steven
** -CWhyte to contact DL to clarify their [[Hall_Task_List_Spring17|Hall Task List]] items-
25 1 Boyd, Steven
** The Picologger has been disconnected. SBoyd to check with CWhyte whether we want it or not
26 7 Boyd, Steven
*** _Contacted Colin/Josef : Josef will meet with John Cobb on Friday to discuss this in the context of ramping the FC_
27 9 Boyd, Steven
** -HNebrensky to send BLOC-chasing email-
28 1 Boyd, Steven
29
* DC Update
30
* LH2 Update 
31 2 Boyd, Steven
* Tracker Update
32 1 Boyd, Steven
* [[Hall_Task_List_Spring17|List of Hall activities in the shutdown]] (Colin) 
33
* Schedule for startup
34 8 Boyd, Steven
** Startup run on Monday May 8th - Hall should be reserved for operations activities all day. Controlled Entry is possible
35
but only when permitted by the MOM.
36 5 Boyd, Steven
** We will *not* be running the SS magnets this user cycle, or taking data with Neon.
37
** We will need to run the FC at some point.
38
** Co-ordination between DC and MOM will be key.
39 1 Boyd, Steven
40
AOB:
41
42
* Last meeting : [[20170425|Tuesday Apr 25 2017]]
43 10 Nebrensky, Henry
* Next meeting : [[20170509|Tuesday May 9 2017]]