20170131 » History » Revision 4

« Previous | Revision 4/21 (diff) | Next »
Boyd, Steven, 30 January 2017 09:39


Ops/Comm Scheduling meeting

Location : G06 in R66 at 2pm

Phone access : ReadyTalk number
US 866-740-1260
UK 0800-496-0576
Swiss 0800-70-53-51
Italy 800182592
Access Code: 2155402

  • SS Magnet status
  • Hydrogen status
  • Issues arising from previous running
  • Operations :
    • C&M System Check status (Ajit/Ed)
    • Establishing a timetable for the runup : when should systems (including magnets) be ready for running?
      • Beam schedule
        • Run up on Jan 30 - Feb 12.
        • Start of user cycle : Feb 14
        • Start of data-taking : Feb 15
      • Reserve shifter support from Feb 10 - Feb 14 (Includes a weekend though)
      • MOM formally starts on Feb 9 (but should be present for the runup activities but will not be on 24-hour call)
      • Possible runup plan (framework for discussion)
        • Bring up magnets to running configuration, take some pulser data and take magnets down (1 day during week of Feb 6 - 9 - which date)
        • Expert led run on Fri Feb 10 or Sat Feb 11 (?) + Beam tune
        • Triage actions of expert led run on Mon Feb 13
        • Bring up magnets on Feb 14, with overnight monitoring by reserve shift.
        • Data-taking start at 08:00 on Feb 15
  • Shift signup for first half of Feb is viable now (but not full)
Shift Block ID # signed up # shifters still needed
1 6 0
2 4 2
3 4 2
4 4 1
Note that in the last 3 shift blocks we still need at least one more shifter overnight for magnet
monitoring. Otherwise we will have to rearrange the shift and take only 1 data-taking shift with 2
magnet monitoring shifts.
  • BLOCs are needed
  • AOB:

Updated by Boyd, Steven almost 7 years ago · 4 revisions